5003 N FIGUEROA ST 90042
Certificate Information: 5003 N FIGUEROA ST 90042
- Application / Permit
- 20016-10000-13389
- Plan Check / Job No.
- B20LA09969
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Auto Repair Garage
- Work Description
- Change of use to convert existing portion of auto repair garage to beauty salon.
- Permit Issued
- Issued on 9/18/2020
- Issuing Office
- Current Status
- CofO Issued on 9/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2020 | SHANGQIN XIE |
| Corrections Issued | 6/8/2020 | SHANGQIN XIE |
| Plan Check Approved | 8/20/2020 | RICARDO RAMIREZ |
| Issued | 9/18/2020 | APPLICANT |
| Building Plans Picked Up | 9/24/2020 | APPLICANT |
| CofO in Progress | 9/7/2021 | ERNESTO CORRAL |
| CofO Issued | 9/7/2021 | ERNESTO CORRAL |
| Permit Finaled | 9/7/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 7/29/2020 | RUBEN VASQUEZ |
| "Q" conditions | Cleared | 7/29/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 7/29/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 7/29/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 7/29/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 7/29/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 7/29/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 7/29/2020 | RUBEN VASQUEZ |
| HPOZ | Cleared | 7/30/2020 | KATIE DEBIASE |
| Historic monument | Cleared | 7/30/2020 | KATIE DEBIASE |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 8/10/2020 | ELENA LOPEZ |
| Specific Plan | Cleared | 8/12/2020 | ADRINEH MELKONIAN |
Contact Information
| Architect | Kapoor,, Daveed Federico; Lic. No.: C32812 | 828 SOLANO AVENUE LOS ANGELES, CA 90012 |
| Contractor | Owner-Builder | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/5/2021 | Partial Approval | LANNY MERRICK |
| Pre-Inspection | 1/5/2021 | Conditional Approval | LANNY MERRICK |
| Final | 2/23/2021 | Partial Approval | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 2/23/2021 | SGSOV Approved | RONALD PACHECO |
| Smoke Detectors | 2/23/2021 | Approved | RONALD PACHECO |
| Wood Frame | 2/23/2021 | Approved | RONALD PACHECO |
| Final | 3/3/2021 | Partial Inspection | RONALD PACHECO |