2113 W ADDISON WAY 90041
Certificate Information: 2113 W ADDISON WAY 90041
- Application / Permit
- 20016-10000-13267
- Plan Check / Job No.
- B20LA09883
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING STORAGE INTO ADU WITH AN ADDITION 1-STORY PER STATE LAW GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/3/2021
- Issuing Office
- Current Status
- CofO Issued on 5/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2020 | CARLOS MONTES |
| Corrections Issued | 6/25/2020 | CARLOS MONTES |
| Quality Review Completed | 7/30/2020 | PRANITA SHAH |
| Building Plans Picked Up | 8/5/2020 | APPLICANT |
| Applicant returned to address corrections | 2/10/2021 | CARLOS MONTES |
| Plan Check Approved | 4/29/2021 | CARLOS MONTES |
| Issued | 5/3/2021 | APPLICANT |
| CofO in Progress | 5/1/2025 | JEFFREY MEAD |
| No Progress | 5/2/2025 | CHARLES BOGHOSKHAN |
| CofO in Progress | 5/2/2025 | CHARLES BOGHOSKHAN |
| Permit Finaled | 5/20/2025 | DEROLD HAUFF |
| Permit Finaled | 5/20/2025 | DEROLD HAUFF |
| CofO Issued | 5/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/24/2021 | MARTIN FRAGOSO |
| Address approval | Cleared | 4/16/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 4/16/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 4/20/2021 | RENZ SORIANO |
| GPI Written Notices | Cleared | 4/22/2021 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 4/22/2021 | CARLOS MONTES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/23/2023 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/3/2023 | Approved | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 4/4/2023 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/25/2023 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 5/25/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/9/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 6/9/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/9/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 6/9/2023 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 6/20/2023 | Corrections Issued | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 6/22/2023 | Corrections Issued | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 6/22/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/5/2023 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 7/5/2023 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 7/5/2023 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/11/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 7/11/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/18/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 7/18/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/18/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 7/25/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 7/25/2023 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 8/4/2023 | Approved | JOSH MEISTER |
| Shower Pan | 9/6/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/2/2023 | Approved | ROY SPAULDING |
| Underground Mechanical | 12/18/2023 | Approved | ROY SPAULDING |
| Underground Mechanical | 1/17/2024 | Partial Approval | CRAIG VAUGHAN |
| Gas Test | 3/14/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 3/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 3/29/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 4/2/2024 | Approved | CRAIG VAUGHAN |
| Final | 10/22/2024 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 10/22/2024 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 10/22/2024 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 3/21/2025 | SGSOV Not Ready | JEFFREY MEAD |
| Final | 4/1/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 4/1/2025 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/1/2025 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 4/1/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 4/4/2025 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 4/4/2025 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 4/4/2025 | Approved | JEFFREY MEAD |
| Final | 5/1/2025 | OK to Issue CofO | JEFFREY MEAD |
| Green Building Final | 5/1/2025 | Approved | JEFFREY MEAD |