5151 N ROCKLAND AVE 90041

Certificate Information: 5151 N ROCKLAND AVE 90041

Application / Permit
20016-10000-13246
Plan Check / Job No.
B20LA09872
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage to new ADU with addition of new kitchen area.
Permit Issued
Issued on 2/9/2021
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 JOE VO
Corrections Issued 6/19/2020 JOE VO
Quality Review Completed 6/29/2020 PRANITA SHAH
Applicant returned to address corrections 9/11/2020 JOE VO
Plan Check Approved 9/16/2020 JOE VO
Issued 2/9/2021 APPLICANT
CofO in Progress 7/21/2022 CRAIG VAUGHAN
Permit Finaled 8/2/2022 DEROLD HAUFF
CofO Issued 8/2/2022 DEROLD HAUFF
Permit Finaled 8/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/4/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/4/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 9/4/2020 RENZ SORIANO
Sewer availability Cleared 9/16/2020 RENZ SORIANO
Grading Pre-Inspection Cleared 1/26/2021 PRANITA SHAH
Construction near power lines Cleared 2/5/2021 RIDWAN HARDY

Contact Information

Contractor Ideal City Construction Inc; Lic. No.: 1017437-B 1825 S EL MOLINO AVE      SAN MARINO, CA 91108

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/23/2021 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 2/23/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 2/25/2021 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 2/25/2021 Approved SCOTT FINNILA
PLUMBING-Rough 2/25/2021 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 3/10/2021 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 3/10/2021 Approved CRAIG VAUGHAN
Wood Frame 3/10/2021 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 5/4/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 5/4/2021 Approved BRIAN SULLIVAN
Sewer 5/4/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 6/3/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 6/3/2021 Approved CRAIG VAUGHAN
Grounding or Bonding 6/3/2021 Approved CRAIG VAUGHAN
HVAC-Rough 6/3/2021 Approved CRAIG VAUGHAN
Shower Pan 6/3/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 6/14/2021 Approved CRAIG VAUGHAN
Insulation 6/14/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 6/14/2021 Partial Approval CRAIG VAUGHAN
Shower Pan 6/14/2021 Not Ready for Inspection CRAIG VAUGHAN
Drywall Nailing 10/21/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/21/2021 Not Ready for Inspection LILIANA PORTILLO
Shower Pan 10/21/2021 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 11/17/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Shower Pan 11/17/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/19/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 7/19/2022 Approved CRAIG VAUGHAN
Final 7/19/2022 OK to Issue CofO CRAIG VAUGHAN
Footing/Foundation/Slab 7/19/2022 Approved CRAIG VAUGHAN
Green Building Final 7/19/2022 Approved CRAIG VAUGHAN
HVAC-Final 7/19/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 7/19/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 7/19/2022 Approved CRAIG VAUGHAN