4240 S FIGUEROA ST 90037
Certificate Information: 4240 S FIGUEROA ST 90037
- Application / Permit
- 20016-10000-13125
- Plan Check / Job No.
- B20LA09793
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (2) STEEL SPECIAL CANTILEVER COLUMNS
- Permit Issued
- Issued on 1/10/2022
- Issuing Office
- Current Status
- CofC Issued on 3/22/2022
Permit Application Status History
| Submitted | 6/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2020 | YOUNG KIM |
| Corrections Issued | 7/7/2020 | YOUNG KIM |
| Quality Review Completed | 7/8/2020 | SAI KHUM |
| Applicant returned to address corrections | 2/8/2021 | YOUNG KIM |
| Applicant returned to address corrections | 5/25/2021 | YOUNG KIM |
| Plan Check Approved | 6/14/2021 | YOUNG KIM |
| Issued | 1/10/2022 | APPLICANT |
| OK for CofC | 3/17/2022 | DARRYL ARNOLD |
| CofC Issued | 3/22/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 11/4/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 11/6/2020 | DAVID URITA |
| Community Plan Implem. Overlay | Cleared | 1/14/2021 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 1/19/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | THOMAS LANG |
| Tenant Habitability Plan | Cleared | 1/3/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | PO BOX 857 VERDUGO CITY, CA 91046 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/3/2022 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 2/10/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 2/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 2/23/2022 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 2/24/2022 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 2/24/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 2/24/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 2/25/2022 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 3/1/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/4/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 3/17/2022 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 3/17/2022 | Approved | DARRYL ARNOLD |