2031-2033 S GAFFEY ST 90731
Certificate Information: 2031-2033 S GAFFEY ST 90731
- Application / Permit
- 20016-10000-13090
- Plan Check / Job No.
- B20LA09789
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Convert half of existing attached 4-car garage into accessory dwelling unit per State Law GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- CofO Issued on 1/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | VU NGUYEN |
| Corrections Issued | 6/12/2020 | VU NGUYEN |
| Quality Review Completed | 6/17/2020 | TU HUA |
| Applicant returned to address corrections | 6/19/2020 | VU NGUYEN |
| Plan Check Approved | 7/7/2020 | VU NGUYEN |
| Issued | 8/19/2020 | APPLICANT |
| CofO in Progress | 12/30/2021 | ANSON MAGLASANG |
| Permit Finaled | 1/3/2022 | DEROLD HAUFF |
| CofO Issued | 1/3/2022 | DEROLD HAUFF |
| Permit Finaled | 1/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | CHINH DINH |
| Sewer availability | Cleared | 6/18/2020 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 9/1/2020 | Not Ready for Inspection | JOHN KLARIN |
| Pre-Inspection | 9/1/2020 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 3/9/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 3/9/2021 | Approved | JOHN KLARIN |
| Insulation | 3/18/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 3/26/2021 | Approved | JOHN KLARIN |
| Gas Test | 10/1/2021 | Approved | JOHN KLARIN |
| Final | 12/17/2021 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 12/17/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 12/17/2021 | SGSOV Not Ready | ANSON MAGLASANG |
| Smoke Detectors | 12/17/2021 | Approved | ANSON MAGLASANG |
| Final | 12/23/2021 | Corrections Issued | ANSON MAGLASANG |
| Green Building Final | 12/23/2021 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 12/23/2021 | SGSOV Approved | ANSON MAGLASANG |
| Final | 12/29/2021 | OK to Issue CofO | ANSON MAGLASANG |