6228 W ORANGE ST 90048
Certificate Information: 6228 W ORANGE ST 90048
- Application / Permit
- 20016-10000-13074
- Plan Check / Job No.
- B20LA09773
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. (1) SHEAR WALL.
- Permit Issued
- Issued on 3/4/2022
- Issuing Office
- Current Status
- CofC Issued on 8/18/2022
Permit Application Status History
| Submitted | 6/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2020 | JESSE VIDUYA |
| Corrections Issued | 7/1/2020 | JESSE VIDUYA |
| Quality Review Completed | 7/8/2020 | SAI KHUM |
| Applicant returned to address corrections | 10/21/2020 | JESSE VIDUYA |
| Plan Check Approved | 10/29/2020 | JESSE VIDUYA |
| No Progress | 2/16/2022 | JESSE VIDUYA |
| Plan Check Approved | 2/16/2022 | JESSE VIDUYA |
| Issued | 3/4/2022 | APPLICANT |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| OK for CofC | 8/17/2022 | DARRYL ARNOLD |
| CofC Issued | 8/18/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 12/10/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Rigid Design & Construction Inc; Lic. No.: 947498-B | 16501 VENTURA BLVD. STE 400 ENCINO, CA 91436 |
| Engineer | Bayat,, Hooman; Lic. No.: C79761 | 14813 MORRISON ST SHERMAN OAKS, CA 91403 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2022 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 4/14/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 5/10/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 5/10/2022 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2022 | Approved | JONATHAN QUACH |
| Footing/Foundation/Slab | 5/27/2022 | Approved | JONATHAN QUACH |
| Wood Frame | 5/27/2022 | Approved | JONATHAN QUACH |
| Deputy Reinf. Concrete | 6/9/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 6/24/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 8/17/2022 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 8/17/2022 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 8/17/2022 | Approved | DARRYL ARNOLD |