5181 W JEFFERSON BLVD 90016
Certificate Information: 5181 W JEFFERSON BLVD 90016
- Application / Permit
- 20016-10000-13063
- Plan Check / Job No.
- B20LA09761
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (3) STEEL SPECIAL CANTILEVERED COLUMNS. REDUCED (1) PARKING SPACE FROM (7) EXISTING PARKING STALLS TO PROVIDE SOFT STORY RETROFIT SYSTEM.
- Permit Issued
- Issued on 12/30/2020
- Issuing Office
- Current Status
- CofC Issued on 5/11/2021
- Certificate of Occupancy
- CofC Issued More Information
Permit Application Status History
| Submitted | 6/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2020 | YOUNG KIM |
| Corrections Issued | 6/30/2020 | YOUNG KIM |
| Quality Review Completed | 7/2/2020 | SAI KHUM |
| Building Plans Picked Up | 7/16/2020 | APPLICANT |
| Applicant returned to address corrections | 10/21/2020 | YOUNG KIM |
| Plan Check Approved | 11/18/2020 | YOUNG KIM |
| Issued | 12/30/2020 | APPLICANT |
| OK for CofC | 4/16/2021 | DARRYL ARNOLD |
| CofC Issued | 5/11/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 7/30/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 8/4/2020 | GRACIELA ACOSTA |
| Community Plan Implem. Overlay | Cleared | 9/30/2020 | KYLE WINSTON |
| Tenant Habitability Plan | Cleared | 12/24/2020 | ISMAEL HERNANDEZ |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Ark Construction Co; Lic. No.: 471822-B | 6131 SAN VICENTE BLVD LOS ANGELES, CA 90048 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2021 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 3/2/2021 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 3/18/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 3/23/2021 | Approved | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 3/30/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 3/30/2021 | Conditional Approval | DARRYL ARNOLD |
| FLOOD-Proofing Certificate | 3/31/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/31/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 3/31/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/6/2021 | Approved | DARRYL ARNOLD |
| FLOOD-Proofing Certificate | 4/16/2021 | Approved | DARRYL ARNOLD |
| Final | 4/16/2021 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/16/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 4/16/2021 | Approved | DARRYL ARNOLD |