11117-11119 W HERSHEY ST 91352

Certificate Information: 11117-11119 W HERSHEY ST 91352

Application / Permit
20016-10000-12964
Plan Check / Job No.
B20LA09701
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. CONVERT PORTION OF (E) SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT PER STATE LAW.
Permit Issued
Issued on 9/15/2020
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2020 APPLICANT
Assigned to Plan Check Engineer 6/4/2020 KEVIN MORALES
Corrections Issued 6/8/2020 KEVIN MORALES
Quality Review Completed 6/23/2020 PRANITA SHAH
Building Plans Picked Up 7/21/2020 APPLICANT
Plan Check Approved 9/9/2020 KEVIN MORALES
Issued 9/15/2020 APPLICANT
CofO in Progress 11/7/2022 DAVID ANDERSON
CofO Issued 12/24/2022 MICHAEL SMITH
Permit Finaled 12/24/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/8/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/8/2020 GABRIEL ROBLES
Specific Plan Cleared 7/8/2020 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/2/2020 Not Ready for Inspection BEAU COLLINS
Footing/Foundation/Slab 12/2/2020 Corrections Issued BEAU COLLINS
METHANE-Rough 12/2/2020 Not Ready for Inspection BEAU COLLINS
BUILDING-Rough-Frame 2/5/2021 Partial Approval JOHN HAYES
Footing/Foundation/Slab 2/5/2021 Approved JOHN HAYES
METHANE-Rough 2/5/2021 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 10/7/2021 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 10/25/2021 Partial Inspection WILLIAM KUEHN
Sewer 10/25/2021 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 11/8/2021 Approved WILLIAM KUEHN
ELECTRICAL-Rough 11/8/2021 Approved WILLIAM KUEHN
METHANE-Rough 11/8/2021 Approved WILLIAM KUEHN
PLUMBING-Rough 11/8/2021 Approved WILLIAM KUEHN
Wood Frame 11/8/2021 Approved WILLIAM KUEHN
Drywall Nailing 12/9/2021 Approved WILLIAM KUEHN
Shower Pan 12/27/2021 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 1/4/2022 Approved MATTHEW NELSON
Gas Test 9/22/2022 Corrections Issued DAVID ANDERSON
Final 11/3/2022 Corrections Issued DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/3/2022 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 11/3/2022 Approved DAVID ANDERSON
Final 11/7/2022 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Approved DAVID ANDERSON
Service/Power Release 11/7/2022 Approved DAVID ANDERSON