8548 N BOTHWELL ROAD 91324
Certificate Information: 8548 N BOTHWELL ROAD 91324
- Application / Permit
- 20016-10000-12959
- Plan Check / Job No.
- B20LA09696
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER STATE LAW. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 8/6/2020
- Issuing Office
- Current Status
- CofO Issued on 10/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 8/6/2020 | AUNG SOE |
| Issued | 8/6/2020 | APPLICANT |
| Building Plans Picked Up | 8/10/2020 | APPLICANT |
| CofO in Progress | 10/20/2020 | JEFFREY PARD |
| CofO Issued | 10/21/2020 | JOHN JANSON |
| Permit Finaled | 10/21/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 7/2/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/2/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Cavalier Builders Inc; Lic. No.: 758563-B | 6520 PLATT AVE #732 WEST HILLS, CA 91307 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/7/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/7/2020 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/12/2020 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 8/12/2020 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 8/12/2020 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 8/17/2020 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/17/2020 | Approved | JEFFREY PARD |
| Sewer | 8/17/2020 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 8/19/2020 | Partial Approval | JEFFREY PARD |
| Wood Frame | 8/19/2020 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 8/24/2020 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 8/26/2020 | Approved | JEFFREY PARD |
| Insulation | 8/28/2020 | Approved | JEFFREY PARD |
| Shower Pan | 8/28/2020 | Approved | JEFFREY PARD |
| Wood Frame | 9/1/2020 | Approved | JEFFREY PARD |
| Drywall Nailing | 9/4/2020 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 9/9/2020 | Approved | JEFFREY PARD |
| Gas Test | 9/15/2020 | Approved | JEFFREY PARD |
| Gas Test | 9/18/2020 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/29/2020 | Approved | JEFFREY PARD |
| Final | 9/29/2020 | Corrections Issued | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 9/29/2020 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 9/29/2020 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 10/8/2020 | No Access for Inspection | JEFFREY PARD |
| Final | 10/8/2020 | No Access for Inspection | JEFFREY PARD |
| HVAC-Final | 10/8/2020 | No Access for Inspection | JEFFREY PARD |
| PLUMBING-Final | 10/8/2020 | No Access for Inspection | JEFFREY PARD |
| ELECTRICAL-Final | 10/19/2020 | Approved | JEFFREY PARD |
| Final | 10/19/2020 | OK to Issue CofO | JEFFREY PARD |
| HVAC-Final | 10/19/2020 | Approved | JEFFREY PARD |
| PLUMBING-Final | 10/19/2020 | Approved | JEFFREY PARD |