627 E COLDEN AVE 90002

Certificate Information: 627 E COLDEN AVE 90002

Application / Permit
20016-10000-12801
Plan Check / Job No.
B20LA09620
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF EXISTING DETACHED GARAGE (289 sf) TO AN ADU WITH AN ATTACHED PATIO COVER (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 3/4/2022
Issuing Office
Current Status
CofO Issued on 5/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2020 APPLICANT
Assigned to Plan Check Engineer 6/17/2020 LUKE GONZALES
Corrections Issued 6/18/2020 LUKE GONZALES
Applicant returned to address corrections 7/13/2020 RICARDO RAMIREZ
Applicant returned to address corrections 10/14/2021 LUKE GONZALES
Applicant returned to address corrections 1/7/2022 SINA KHOSRAVI
Plan Check Approved 2/23/2022 AUNG SOE
Issued 3/4/2022 APPLICANT
Building Plans Picked Up 3/7/2022 APPLICANT
CofO in Progress 3/21/2023 JOHN KLARIN
Permit Finaled 5/10/2023 DANIEL ORRANTE
CofO Issued 5/10/2023 DANIEL ORRANTE
Permit Finaled 5/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/24/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 4/7/2021 RENZ SORIANO
Construction near power lines Cleared 4/12/2021 RIDWAN HARDY
Sewer availability Cleared 9/7/2021 RENZ SORIANO
Low Impact Development Cleared 12/9/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/16/2021 AMAAN MALIK
Hold Cleared 6/14/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/22/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/10/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 8/10/2022 Approved JOHN KLARIN
Green Building Rough 8/10/2022 Approved JOHN KLARIN
PLUMBING-Rough 8/10/2022 Approved JOHN KLARIN
Underground Mechanical 8/10/2022 Partial Approval JOHN KLARIN
Insulation 8/18/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 8/18/2022 Approved JOHN KLARIN
Drywall Nailing 8/23/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/30/2022 Approved JOSEPH MCGARRY
Shower Pan 8/30/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Final 9/19/2022 Approved ALIZAH MAYAGOITIA
Final 9/19/2022 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 9/19/2022 Approved ALIZAH MAYAGOITIA
Green Building Final 9/19/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 9/19/2022 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 9/19/2022 Approved ALIZAH MAYAGOITIA
Final 9/29/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 9/29/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 9/29/2022 SGSOV Not Ready ALIZAH MAYAGOITIA
Green Building Final 10/5/2022 Approved ALIZAH MAYAGOITIA
Final 12/6/2022 Corrections Issued JOHN KLARIN
Green Building Final 12/6/2022 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Approved JOHN KLARIN
Final 12/15/2022 Not Ready for Inspection JOHN KLARIN
Green Building Final 12/15/2022 Approved JOHN KLARIN
Final 2/15/2023 Corrections Issued JOHN KLARIN
HVAC-Final 2/15/2023 Approved JOHN KLARIN
Final 3/20/2023 OK to Issue CofO JOHN KLARIN
PLUMBING-Final 3/20/2023 Approved JOHN KLARIN