2183 N KENILWORTH AVE 90039

Certificate Information: 2183 N KENILWORTH AVE 90039

Application / Permit
20016-10000-12768
Plan Check / Job No.
B20LA09602
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL WITH CHANGING OF WINDOWS AND DOORS. CONVERTING GARAGE ROOF TO DECK.
Permit Issued
Issued on 10/14/2020
Issuing Office
Current Status
CofO Issued on 11/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 CRYSTEL MAALOUF
Corrections Issued 7/7/2020 CRYSTEL MAALOUF
Quality Review Completed 8/13/2020 TU HUA
Building Plans Picked Up 8/17/2020 APPLICANT
Plan Check Approved 10/9/2020 CRYSTEL MAALOUF
Issued 10/14/2020 APPLICANT
CofO in Progress 10/29/2021 JOSEPH MCGARRY
Permit Finaled 11/6/2021 DEROLD HAUFF
CofO Issued 11/6/2021 DEROLD HAUFF
Permit Finaled 11/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/17/2020 BARTON HOLMES
Eng Process Fee Ord 176,300 Cleared 9/25/2020 WALLIE JONG
Roof/Waste drainage to street Cleared 9/25/2020 WALLIE JONG

Contact Information

Contractor Luis Chavez Construction Inc; Lic. No.: 1024942-B P O BOX 36824      LOS ANGELES, CA 90036
Engineer Chen,, Emily Hsiao Han; Lic. No.: C73319 22629 LAKESIDE LN      LAKE FOREST, CA 926303035

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/16/2020 Approved DONALD CRICHLOW
Footing/Foundation/Slab 11/16/2020 Approved DONALD CRICHLOW
Piling/Pier/Caisson 11/16/2020 Approved DONALD CRICHLOW
Deputy Steel/Welding 12/17/2020 Partial Approval JOSEPH MCGARRY
Wood Frame 1/19/2021 Partial Inspection JOSEPH MCGARRY
Deputy Wood Construction 2/8/2021 Partial Approval JOSEPH MCGARRY
Structural Steel Frame 2/8/2021 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 2/8/2021 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 2/19/2021 Approved JOSEPH MCGARRY
Insulation 3/1/2021 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/1/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 3/3/2021 Approved JOSEPH MCGARRY
Final 8/17/2021 Not Ready for Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 8/17/2021 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 8/17/2021 Approved JOSEPH MCGARRY
Final 10/25/2021 Corrections Issued JOSEPH MCGARRY
Final 10/28/2021 OK to Issue CofO JOSEPH MCGARRY