218 S AVENUE 58 90042

Certificate Information: 218 S AVENUE 58 90042

Application / Permit
20016-10000-12747
Plan Check / Job No.
B20LA09580
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN 5472 - Soft-Story seismic retrofit per LABC Chapter 93: INSTALL PLYWOOD SHEAR WALL.
Permit Issued
Issued on 10/8/2020
Issuing Office
Current Status
CofC Issued on 12/22/2020

Permit Application Status History

Submitted 6/17/2020 APPLICANT
Assigned to Plan Check Engineer 7/15/2020 VARAND SARKISIAN
Corrections Issued 7/27/2020 VARAND SARKISIAN
Quality Review Completed 7/28/2020 SAI KHUM
Applicant returned to address corrections 8/13/2020 VARAND SARKISIAN
Plan Check Approved 9/11/2020 VARAND SARKISIAN
Issued 10/8/2020 APPLICANT
OK for CofC 12/16/2020 MARK FERRARI
CofC Issued 12/22/2020 ERNESTO CORRAL

Permit Application Clearance Information

HPOZ Cleared 8/20/2020 KATIE DEBIASE
Tenant Habitability Plan Cleared 10/7/2020 PHILLIP MUNGUIA

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B 19562 VENTURA BLVD# 230      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/23/2020 Approved MARK FERRARI
Footing/Foundation/Slab 10/30/2020 Approved MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Not Ready for Inspection MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 11/12/2020 Not Ready for Inspection MARK FERRARI
Deputy Wood Construction 11/25/2020 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 11/25/2020 Not Ready for Inspection MARK FERRARI
Reinforced Concrete Frame 11/25/2020 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 11/25/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 11/25/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 12/3/2020 Partial Approval MARK FERRARI
Deputy Wood Construction 12/8/2020 Approved MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 12/8/2020 Corrections Issued MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Partial Approval DARRYL ARNOLD
Wood Frame 12/10/2020 Partial Approval DARRYL ARNOLD
Interior/Exterior Lathing 12/11/2020 Approved DARRYL ARNOLD
Final 12/16/2020 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 12/16/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 12/16/2020 Approved MARK FERRARI