1182 W 24TH ST 90731
Certificate Information: 1182 W 24TH ST 90731
- Application / Permit
- 20016-10000-12677
- Plan Check / Job No.
- B20LA09523
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING GARAGE & ROOM TO ACCESSORY DWELLING UNIT PER ORDINANCE
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- CofO Issued on 10/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/2/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 6/30/2020 | SINA KHOSRAVI |
| Plan Check Approved | 6/30/2020 | SINA KHOSRAVI |
| No Progress | 7/2/2020 | SINA KHOSRAVI |
| Building Plans Picked Up | 7/6/2020 | APPLICANT |
| Plan Check Approved | 7/15/2020 | STARR CHEN |
| Issued | 7/17/2020 | APPLICANT |
| CofO in Progress | 10/18/2023 | JAMES CHAVEZ |
| CofO Issued | 10/20/2023 | ANSON MAGLASANG |
| Permit Finaled | 10/20/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2020 | CHINH DINH |
| Sewer availability | Cleared | 6/15/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2020 | CHINH DINH |
| Grading Pre-Inspection | Cleared | 6/17/2020 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/10/2020 | Approved | JOHN KLARIN |
| Deputy Drilled-In Anchors | 9/3/2020 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 9/3/2020 | Conditional Approval | JOHN KLARIN |
| Underground Mechanical | 9/3/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Partial Approval | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 9/30/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Sewer | 9/30/2022 | Approved | EUGENE CASSIDY |
| Wood Frame | 9/30/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/13/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Rough | 10/13/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 10/13/2022 | Partial Approval | ANSON MAGLASANG |
| Underground Mechanical | 10/13/2022 | Partial Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 12/14/2022 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Approved | JOHN KLARIN |
| HVAC-Rough | 12/14/2022 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 12/14/2022 | Approved | JOHN KLARIN |
| Wood Frame | 12/14/2022 | Approved | JOHN KLARIN |
| Insulation | 2/13/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 2/24/2023 | Not Ready for Inspection | JOHN KLARIN |
| Drywall Nailing | 3/3/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 3/21/2023 | Partial Approval | JAMES CHAVEZ |
| Shower Pan | 3/21/2023 | Approved | JAMES CHAVEZ |
| Special/Order Compliance | 8/15/2023 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 9/29/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 9/29/2023 | Corrections Issued | JAMES CHAVEZ |
| Final | 9/29/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Final | 9/29/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Final | 9/29/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 9/29/2023 | SGSOV Not Ready | JAMES CHAVEZ |
| Service/Power Release | 9/29/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 9/29/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 10/12/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 10/12/2023 | Corrections Issued | JAMES CHAVEZ |
| HVAC-Final | 10/12/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 10/12/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 10/12/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 10/12/2023 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Final | 10/18/2023 | Approved | JAMES CHAVEZ |
| Final | 10/18/2023 | OK to Issue CofO | JAMES CHAVEZ |
| HVAC-Final | 10/18/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 10/18/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 10/18/2023 | Not Ready for Inspection | JAMES CHAVEZ |