8104-8106 S FLIGHT AVE 90045

Certificate Information: 8104-8106 S FLIGHT AVE 90045

Application / Permit
20016-10000-12612
Plan Check / Job No.
B20LA09481
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF EXISTING ONE-FAMILY DWELLING T O JUNIOR ADU GOVERNMENT LAW GCS
Permit Issued
Issued on 11/2/2020
Issuing Office
Current Status
CofO Issued on 4/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 MAHNAZ NOURHASHEMI
Corrections Issued 6/25/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 7/1/2020 TIEN JEN WANG
Plan Check Approved 9/21/2020 MAHNAZ NOURHASHEMI
Plan Check Approved 10/7/2020 MAHNAZ NOURHASHEMI
Issued 11/2/2020 APPLICANT
Building Plans Picked Up 11/6/2020 APPLICANT
CofO in Progress 4/20/2022 BOBBY KEY
Permit Finaled 4/26/2022 DANIEL ORRANTE
CofO Issued 4/26/2022 DANIEL ORRANTE
Permit Finaled 4/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/23/2020 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 7/23/2020 CATHERINE ADROVER
Sewer availability Cleared 7/23/2020 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 7/30/2020 CATHERINE ADROVER
Green Code Cleared 9/1/2020 MAHNAZ NOURHASHEMI
Specific Plan Cleared 9/10/2020 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/19/2021 Partial Inspection JUAN VALENZUELA
Underground Mechanical 3/1/2021 Approved DAVID HEINE
Deputy Drilled-In Anchors 4/26/2021 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Rough 6/28/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 6/28/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 6/28/2021 Not Ready for Inspection BRENDAN LOONEY
Deputy Drilled-In Anchors 6/29/2021 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Rough 7/13/2021 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 7/13/2021 Partial Approval BRENDAN LOONEY
Wood Frame 7/13/2021 Conditional Approval BRENDAN LOONEY
BUILDING-Rough-Frame 7/15/2021 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 7/15/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 7/15/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 7/15/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 7/15/2021 Not Ready for Inspection BRENDAN LOONEY
Service/Power Release 7/15/2021 Not Ready for Inspection BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 7/21/2021 Conditional Approval BRENDAN LOONEY
Service/Power Release 7/21/2021 Corrections Issued BRENDAN LOONEY
Service/Power Release 8/2/2021 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 9/3/2021 Corrections Issued BRENDAN LOONEY
Service/Power Release 9/3/2021 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 9/21/2021 Corrections Issued BRENDAN LOONEY
Green Building Rough 9/21/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 9/30/2021 Corrections Issued BRENDAN LOONEY
Drywall Nailing 9/30/2021 Not Ready for Inspection BRENDAN LOONEY
Final 9/30/2021 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 9/30/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Final 9/30/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 9/30/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 1/5/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 1/13/2022 Approved BOBBY KEY
Insulation 1/13/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 1/20/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/20/2022 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 1/20/2022 Approved BOBBY KEY
Drywall Nailing 1/25/2022 Approved BOBBY KEY
Final 1/25/2022 Corrections Issued BOBBY KEY
HVAC-Rough 1/25/2022 Approved BOBBY KEY
Interior/Exterior Lathing 1/31/2022 Approved BOBBY KEY
Shower Pan 1/31/2022 Approved BOBBY KEY
ELECTRICAL-Final 3/1/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 3/29/2022 Partial Approval JESUS RODRIGUEZ
Final 3/29/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 3/29/2022 Approved JESUS RODRIGUEZ
HVAC-Final 3/29/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 3/29/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/29/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 3/29/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 4/4/2022 Approved BOBBY KEY
Final 4/4/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 4/4/2022 Approved BOBBY KEY
PLUMBING-Final 4/4/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 4/4/2022 SGSOV Not Ready BOBBY KEY
Final 4/20/2022 OK to Issue CofO BOBBY KEY
SGSOV-Seismic Gas S/O Valve 4/20/2022 SGSOV Approved BOBBY KEY
Service/Power Release 4/20/2022 Approved BOBBY KEY
Service/Power Release 4/29/2022 Approved RICHARD STEINBACH