990 W 190TH ST 220 90502

Certificate Information: 990 W 190TH ST 220 90502

Application / Permit
20016-10000-12432
Plan Check / Job No.
B20LA09338
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
ePLan TI. Addition of non load bearing walls, doors, sink, addition of mothers room, updated finishes. no change of use, no structural work, no exterior work
Permit Issued
Issued on 11/18/2020
Issuing Office
Metro
Current Status
Permit Finaled on 4/12/2021

Permit Application Status History

Submitted 5/26/2020 APPLICANT
Assigned to Plan Check Engineer 5/27/2020 MONICA RAMIREZ
Corrections Issued 5/28/2020 MONICA RAMIREZ
Applicant returned to address corrections 8/5/2020 MONICA RAMIREZ
Plan Check Approved 11/2/2020 HELEN NGUYEN
Issued 11/18/2020 APPLICANT
Permit Finaled 4/9/2021 JOEY BUCHANAN

Permit Application Clearance Information

Fire Marshall Fire Life Safety Cleared 10/28/2020 DOMINIQUE MEDINA

Contact Information

Architect California, Architects Board; Lic. No.: C38207 21145 QUAY STREET NW      OAK GROVE, MN 5303
Contractor Mata Construction Services Inc; Lic. No.: 842965-B 5016 EAGLE ROCK BLVD      LOS ANGELES, CA 90041

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 12/10/2020 Partial Approval JOEY BUCHANAN
Insulation 12/17/2020 Approved JOEY BUCHANAN
Drywall Nailing 12/23/2020 Approved JOEY BUCHANAN
Light Gage Steel Frame 1/20/2021 Corrections Issued JOEY BUCHANAN
Light Gage Steel Frame 1/25/2021 Partial Approval LEOPOLDO MENDOZA
Pre-Inspection 1/26/2021 Partial Approval LEOPOLDO MENDOZA
T-Bar Ceiling 1/26/2021 Partial Approval LEOPOLDO MENDOZA
T-Bar Ceiling 1/28/2021 Conditional Approval LEOPOLDO MENDOZA
Final 2/26/2021 Not Ready for Inspection JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 2/26/2021 Approved JOEY BUCHANAN
Final 3/1/2021 Not Ready for Inspection JOEY BUCHANAN
Final 3/10/2021 Corrections Issued JOEY BUCHANAN
Final 3/17/2021 Corrections Issued JOEY BUCHANAN
Final 4/9/2021 Permit Finaled JOEY BUCHANAN