847-849 E VENICE BLVD 90291
Certificate Information: 847-849 E VENICE BLVD 90291
- Application / Permit
- 20016-10000-12404
- Plan Check / Job No.
- B20LA09322
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Alteration/repairs to (E) SFD and change of use to SFD with Supportive Services and part of affordability project per LAMC 14.13 (Qualified Permanent Supportive Housing Project).
- Permit Issued
- Issued on 12/6/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 12/3/2021 | RODOLFO ARIAS |
| Issued | 12/6/2021 | APPLICANT |
| TCO Issued (Expire Date: 08-09-2025) | 2/10/2025 | DAVID TSAU |
| CofO in Progress | 5/19/2025 | FARHAD DADBIN |
| Permit Finaled | 5/21/2025 | DAVID TSAU |
| CofO Issued | 5/21/2025 | DAVID TSAU |
| Permit Finaled | 5/21/2025 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2021 | ANTHONY MAINEZ |
| Density Bonus 14.00.A.13 | Cleared | 7/20/2021 | NGHIEM TRAN |
| Specific Plan | Cleared | 7/28/2021 | IRA BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2021 | ANTHONY MAINEZ |
| ZA Case | Cleared | 8/5/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 8/5/2021 | TERRI OSBORNE |
| Coastal Zone | Cleared | 8/25/2021 | ERIC CLAROS |
| Mello Bill | Cleared | 8/25/2021 | ERIC CLAROS |
| ZA Case | Cleared | 8/25/2021 | ERIC CLAROS |
| Specific Plan | Cleared | 8/26/2021 | VALERIA CEJA |
| Miscellaneous | Cleared | 9/7/2021 | TRACY TATE |
| Miscellaneous | Cleared | 9/23/2021 | TERRI OSBORNE |
| DAS Clearance | Cleared | 11/3/2021 | RODOLFO ARIAS |
Contact Information
| Architect | Daly,, Kevin Michael; Lic. No.: C19005 | 3617 W EXPOSITION BLVD LOS ANGELES, CA 90016 |
| Contractor | Perea Construction Services Inc; Lic. No.: 979151-B | 19197 GOLDEN VALLEY RD #548 SANTA CLARITA, CA 91387 |
| Engineer | Adams,, Jelisa Thomas; Lic. No.: GE3092 | 26632 EL TOBOSO MISSION VIEJO, CA 92691 |
| Engineer | Obando,, Gaspar Eduardo; Lic. No.: C71382 | 1453 14TH ST STE A SANTA MONICA, CA 90404 |
| Engineer | Varela, Olivas, Benjamin; Lic. No.: S5714 | 6007 WASHINGTON BLVD CULVER CITY, CA 90232 |
| Geologist | Kirkgard,, Susan Franzen; Lic. No.: EG1754 | 1481 STONEBROOK STREET AZUSA, CA 91702 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 2/9/2022 | Conditional Approval | JOHN DODGE |
| Footing/Foundation/Slab | 2/14/2022 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 2/15/2022 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 2/23/2022 | Approved | GRANT WOODS |
| Deputy Reinf. Concrete | 2/25/2022 | Conditional Approval | GRANT WOODS |
| Green Building Rough | 4/7/2022 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 4/7/2022 | Partial Inspection | GRANT WOODS |
| Green Building Rough | 6/2/2022 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 6/2/2022 | Not Ready for Inspection | GRANT WOODS |
| Deputy Wood Construction | 6/7/2022 | Conditional Approval | SORIN CIRSTOIU |
| Green Building Rough | 6/9/2022 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 6/9/2022 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 6/17/2022 | Partial Approval | SORIN CIRSTOIU |
| Green Building Rough | 6/17/2022 | Partial Inspection | SORIN CIRSTOIU |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Approved | JOEY BUCHANAN |
| Green Building Rough | 10/21/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 10/21/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Green Building Rough | 10/26/2022 | Partial Inspection | SORIN CIRSTOIU |
| Wood Frame | 10/26/2022 | Partial Approval | SORIN CIRSTOIU |
| Green Building Rough | 1/19/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 1/19/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Special/Order Compliance | 1/26/2023 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Rough | 2/1/2023 | Partial Inspection | SORIN CIRSTOIU |
| Pre-Inspection | 2/1/2023 | Partial Inspection | SHAVONNE ESPINOZA |
| Wood Frame | 2/1/2023 | Partial Approval | SORIN CIRSTOIU |
| Deputy Wood Construction | 2/6/2023 | Conditional Approval | SHAVONNE ESPINOZA |
| Green Building Rough | 2/6/2023 | Approved | SORIN CIRSTOIU |
| Insulation | 2/6/2023 | Approved | SORIN CIRSTOIU |
| Wood Frame | 2/6/2023 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 2/10/2023 | Approved | AMANUEL BERHE |
| Interior/Exterior Lathing | 4/26/2023 | Approved | SORIN CIRSTOIU |
| Final | 8/9/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 8/9/2023 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 8/9/2023 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 8/9/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 8/9/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 10/5/2023 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2023 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 10/5/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 10/5/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 12/1/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 12/1/2023 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 12/1/2023 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 12/1/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 12/1/2023 | Partial Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 9/12/2024 | Not Ready for Inspection | AMANUEL BERHE |
| Footing/Foundation/Slab | 9/16/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 10/17/2024 | Partial Approval | FARHAD DADBIN |
| Reinforced Concrete Frame | 10/17/2024 | Partial Approval | FARHAD DADBIN |
| Reinforced Concrete Frame | 11/12/2024 | Partial Approval | FARHAD DADBIN |
| Wood Frame | 1/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 2/3/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 2/3/2025 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 2/3/2025 | Approved | FARHAD DADBIN |
| Wood Frame | 2/3/2025 | Approved | FARHAD DADBIN |
| Final | 5/19/2025 | OK to Issue CofO | FARHAD DADBIN |