2213 S MARIAN PL 90291

Certificate Information: 2213 S MARIAN PL 90291

Application / Permit
20016-10000-12397
Plan Check / Job No.
B20LA09322
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Alteration/repairs to (E) SFD and part of affordability project per LAMC 14.13 (Qualified Permanent Supportive Housing Project).
Permit Issued
Issued on 12/6/2021
Issuing Office
Current Status
Permit Finaled on 9/1/2023

Permit Application Status History

Plan Check Approved 12/3/2021 RODOLFO ARIAS
Issued 12/6/2021 APPLICANT
Permit Finaled 9/1/2023 HERBERT GIRON

Permit Application Clearance Information

Address approval Cleared 6/22/2021 ANTHONY MAINEZ
Density Bonus 14.00.A.13 Cleared 7/20/2021 NGHIEM TRAN
ZA Case Cleared 7/22/2021 TERRI OSBORNE
ZA Case Cleared 7/22/2021 TERRI OSBORNE
Specific Plan Cleared 7/28/2021 IRA BROWN
Eng Process Fee Ord 176,300 Cleared 7/29/2021 ANTHONY MAINEZ
Coastal Zone Cleared 8/25/2021 ERIC CLAROS
ZA Case Cleared 8/25/2021 ERIC CLAROS
Miscellaneous Cleared 9/23/2021 TERRI OSBORNE

Contact Information

Architect Daly,, Kevin Michael; Lic. No.: C19005 3617 W EXPOSITION BLVD      LOS ANGELES, CA 90016
Contractor Perea Construction Services Inc; Lic. No.: 979151-B 19197 GOLDEN VALLEY RD #548      SANTA CLARITA, CA 91387
Engineer Adams,, Jelisa Thomas; Lic. No.: GE3092 26632 EL TOBOSO      MISSION VIEJO, CA 92691
Engineer Obando,, Gaspar Eduardo; Lic. No.: C71382 1453 14TH ST STE A      SANTA MONICA, CA 90404
Engineer Varela, Olivas, Benjamin; Lic. No.: S5714 6007 WASHINGTON BLVD      CULVER CITY, CA 90232
Geologist Kirkgard,, Susan Franzen; Lic. No.: EG1754 1481 STONEBROOK STREET      AZUSA, CA 91702

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/22/2022 Not Ready for Inspection ANDREW NAVE
HVAC-Rough 2/22/2022 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 2/22/2022 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Rough 3/4/2022 Approved DAVID FEILER
HVAC-Rough 3/4/2022 Approved DAVID FEILER
PLUMBING-Rough 3/4/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 3/9/2022 Partial Approval DAVID FEILER
Drywall Nailing 3/18/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 3/18/2022 Approved DAVID FEILER
Drywall Nailing 3/24/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 3/24/2022 Approved STEPHANIE SWANSON
Insulation 4/7/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 6/22/2022 Approved DAVID FEILER
Sewer 9/12/2022 Approved DAVID FEILER
Underground Mechanical 9/12/2022 Partial Approval DAVID FEILER
Underground Mechanical 9/16/2022 Approved DAVID FEILER
HVAC-Final 6/30/2023 Corrections Issued EVAN COOPER
PLUMBING-Final 6/30/2023 Corrections Issued EVAN COOPER
Final 7/27/2023 Conditional Approval EVAN COOPER
Green Building Final 7/27/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/27/2023 SGSOV Approved EVAN COOPER
Smoke Detectors 7/27/2023 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 9/1/2023 Approved HERBERT GIRON
Final 9/1/2023 Permit Finaled HERBERT GIRON
HVAC-Final 9/1/2023 Approved HERBERT GIRON
PLUMBING-Final 9/1/2023 Approved HERBERT GIRON
Smoke Detectors 9/1/2023 Approved HERBERT GIRON