2029 S CENTURY PARK EAST 2500 90067
Certificate Information: 2029 S CENTURY PARK EAST 2500 90067
- Application / Permit
- 20016-10000-12364
- Plan Check / Job No.
- B20LA09310
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR T.I INCLUDING DEMO INTERIOR PARTION WALLS, NEW NON-BEARING PARTITIONS, NEW CEILING AND NEW FINISHES.
- Permit Issued
- Issued on 7/21/2020
- Issuing Office
- Current Status
- Permit Finaled on 6/29/2021
Permit Application Status History
| Submitted | 6/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2020 | RAHEL BEYENE |
| Corrections Issued | 6/17/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 7/1/2020 | TSE MING HUANG |
| Plan Check Approved | 7/8/2020 | FARSHAD ALIMOHAMADI |
| Issued | 7/21/2020 | APPLICANT |
| Building Plans Picked Up | 7/21/2020 | APPLICANT |
| Permit Finaled | 6/28/2021 | PAUL DAVIDSON |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/7/2020 | JOE LUCKEY |
| ZA Case | Cleared | 7/7/2020 | JOE LUCKEY |
Contact Information
| Architect | Swartz,, David Louis; Lic. No.: C19729 | 1437 4TH STREET SUITE 400 SANTA MONICA, CA 90401 |
| Contractor | J T M Construction Group Inc; Lic. No.: 956584-B | 44 WEST 28TH STREET 11TH FLOOR NEW YORK, NY 10001 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/21/2020 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 9/18/2020 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 9/23/2020 | Partial Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 10/1/2020 | No Access for Inspection | PAUL DAVIDSON |
| Light Gage Steel Frame | 10/5/2020 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 10/7/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Light Gage Steel Frame | 10/15/2020 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 10/20/2020 | Approved | PAUL DAVIDSON |
| T-Bar Ceiling | 10/28/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| T-Bar Ceiling | 10/30/2020 | Approved | PAUL DAVIDSON |
| Pre-Inspection | 11/23/2020 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 11/24/2020 | SGSOV Approved | PAUL DAVIDSON |
| Final | 6/28/2021 | Permit Finaled | PAUL DAVIDSON |
| Green Building Final | 6/28/2021 | Approved | PAUL DAVIDSON |
| Green Building Rough | 6/28/2021 | Approved | PAUL DAVIDSON |
| Smoke Detectors | 6/28/2021 | Approved | PAUL DAVIDSON |