2029 S CENTURY PARK EAST 2500 90067

Certificate Information: 2029 S CENTURY PARK EAST 2500 90067

Application / Permit
20016-10000-12364
Plan Check / Job No.
B20LA09310
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
INTERIOR T.I INCLUDING DEMO INTERIOR PARTION WALLS, NEW NON-BEARING PARTITIONS, NEW CEILING AND NEW FINISHES.
Permit Issued
Issued on 7/21/2020
Issuing Office
Current Status
Permit Finaled on 6/29/2021

Permit Application Status History

Submitted 6/8/2020 APPLICANT
Assigned to Plan Check Engineer 6/8/2020 RAHEL BEYENE
Corrections Issued 6/17/2020 RAHEL BEYENE
Applicant returned to address corrections 7/1/2020 TSE MING HUANG
Plan Check Approved 7/8/2020 FARSHAD ALIMOHAMADI
Issued 7/21/2020 APPLICANT
Building Plans Picked Up 7/21/2020 APPLICANT
Permit Finaled 6/28/2021 PAUL DAVIDSON

Permit Application Clearance Information

Miscellaneous Cleared 7/7/2020 JOE LUCKEY
ZA Case Cleared 7/7/2020 JOE LUCKEY

Contact Information

Architect Swartz,, David Louis; Lic. No.: C19729 1437 4TH STREET SUITE 400      SANTA MONICA, CA 90401
Contractor J T M Construction Group Inc; Lic. No.: 956584-B 44 WEST 28TH STREET 11TH FLOOR      NEW YORK, NY 10001

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 8/21/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 9/18/2020 Partial Approval PAUL DAVIDSON
Drywall Nailing 9/23/2020 Partial Approval PAUL DAVIDSON
Light Gage Steel Frame 10/1/2020 No Access for Inspection PAUL DAVIDSON
Light Gage Steel Frame 10/5/2020 Partial Approval PAUL DAVIDSON
Drywall Nailing 10/7/2020 Not Ready for Inspection PAUL DAVIDSON
Light Gage Steel Frame 10/15/2020 Approved PAUL DAVIDSON
Drywall Nailing 10/20/2020 Approved PAUL DAVIDSON
T-Bar Ceiling 10/28/2020 Not Ready for Inspection PAUL DAVIDSON
T-Bar Ceiling 10/30/2020 Approved PAUL DAVIDSON
Pre-Inspection 11/23/2020 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Approved PAUL DAVIDSON
Final 6/28/2021 Permit Finaled PAUL DAVIDSON
Green Building Final 6/28/2021 Approved PAUL DAVIDSON
Green Building Rough 6/28/2021 Approved PAUL DAVIDSON
Smoke Detectors 6/28/2021 Approved PAUL DAVIDSON