6916 N MCLENNAN AVE 91406

Certificate Information: 6916 N MCLENNAN AVE 91406

Application / Permit
20016-10000-12326
Plan Check / Job No.
B20LA09286
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLan ADUs. convert garage to ADU per state law
Permit Issued
Issued on 9/9/2020
Issuing Office
Current Status
CofO Issued on 4/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2020 APPLICANT
Assigned to Plan Check Engineer 5/28/2020 VU NGUYEN
Corrections Issued 6/3/2020 VU NGUYEN
Quality Review Completed 6/8/2020 TU HUA
Applicant returned to address corrections 8/13/2020 VU NGUYEN
Plan Check Approved 9/3/2020 VU NGUYEN
Issued 9/9/2020 APPLICANT
CofO in Progress 1/13/2021 ARTHUR SARGSYAN
CofO in Progress 1/13/2021 ARTHUR SARGSYAN
CofO Issued 4/24/2021 MICHAEL SMITH
Permit Finaled 4/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Hold Cleared 7/17/2020 JASON SHEETS
Address approval Cleared 7/29/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 7/29/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 7/29/2020 JOHN TRIANTAFYLLOS

Contact Information

No Data Available.

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/15/2020 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 9/15/2020 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 9/15/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/21/2020 Approved MISAEL ESPARZA
PLUMBING-Rough 9/21/2020 Approved MISAEL ESPARZA
PLUMBING-Rough 9/25/2020 Approved BRENDAN LOONEY
Wood Frame 9/25/2020 Partial Approval BRENDAN LOONEY
Insulation 9/28/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 9/28/2020 Partial Inspection WILLIAM KUEHN
Drywall Nailing 10/2/2020 Approved MICHAEL TEMPLE
Sewer 10/8/2020 Approved DAVID MATSON
BUILDING-Rough-Frame 12/24/2020 Approved ARTHUR SARGSYAN
Final 12/24/2020 OK to Issue CofO ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/24/2020 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 12/24/2020 Approved ARTHUR SARGSYAN