5136 E IRVINGTON PL 90042

Certificate Information: 5136 E IRVINGTON PL 90042

Application / Permit
20016-10000-12311
Plan Check / Job No.
B20LA09264
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO DETACHED ADU (1-STORY) CONVERT EXISTING ACCESSORY BUILDING TO DETACHED ADU PER STATE LAW GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/16/2023
Issuing Office
Metro
Current Status
CofO Issued on 6/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 CARLOS MONTES
Corrections Issued 6/23/2020 CARLOS MONTES
Quality Review Completed 7/15/2020 PRANITA SHAH
Green Plans Picked Up 7/20/2020 APPLICANT
Building Plans Picked Up 9/14/2020 APPLICANT
Applicant returned to address corrections 10/30/2020 CARLOS MONTES
Applicant returned to address corrections 5/7/2021 CARLOS MONTES
Applicant returned to address corrections 9/23/2021 CARLOS MONTES
Applicant returned to address corrections 1/24/2022 CARLOS MONTES
Applicant returned to address corrections 9/29/2022 CARLOS MONTES
Applicant returned to address corrections 10/5/2022 CARLOS MONTES
Plan Check Approved 2/21/2023 CARLOS MONTES
Issued 3/16/2023 APPLICANT
CofO in Progress 6/7/2024 THOMAS LOGRASSO
CofO Issued 6/11/2024 DEROLD HAUFF
Permit Finaled 6/11/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/20/2021 CARLOS MONTES
Address approval Cleared 7/28/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 7/28/2022 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 7/28/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 7/28/2022 CHRISTOPHER ROCHA
ZA Case Cleared 11/22/2022 SHASHA YU

Contact Information

Contractor Owner-Builder       ,
Engineer Velasco,, Jose Luis; Lic. No.: C76091 100 SE 2ND STREET SUITE 2000      MIAMI, FL 33131

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/25/2023 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 1/30/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/30/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 1/30/2024 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/6/2024 Approved THOMAS LOGRASSO
Drywall Nailing 6/6/2024 Approved THOMAS LOGRASSO
Final 6/6/2024 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 6/6/2024 Approved THOMAS LOGRASSO
Green Building Rough 6/6/2024 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 6/6/2024 Approved THOMAS LOGRASSO