10307 S RUTHELEN ST 90047

Certificate Information: 10307 S RUTHELEN ST 90047

Application / Permit
20016-10000-12132
Plan Check / Job No.
B20LA09122
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Supplemental to permit #19010-30000-05079 to update address, structural inventory and revise scope of work to: New Accessory Dwelling Unit over slab-on-grade foundation. RADCO approved Factory Built Housing Unit Per: RAD-31-1027 & RAD-31-1028 .
Permit Issued
Issued on 7/7/2020
Issuing Office
Current Status
Permit Finaled on 3/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2020 APPLICANT
Assigned to Plan Check Engineer 5/21/2020 LAMAR DAVIS
Corrections Issued 5/28/2020 LAMAR DAVIS
Quality Review Completed 6/8/2020 TU HUA
Plan Check Approved 6/26/2020 LAMAR DAVIS
Issued 7/7/2020 APPLICANT
Permit Finaled-Status Void 1/13/2021 FREDDIE RIVERA
CofO in Progress 1/14/2021 FREDDIE RIVERA
No Progress 2/3/2021 WILL MCCONNAUGHY
Re-Activate Permit 2/23/2021 FREDDIE RIVERA
Permit Finaled 3/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/9/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/18/2020 CECILIO NAVARRO

Contact Information

Contractor Modative Build Inc; Lic. No.: 957698-B 8757 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2020 Approved FREDDIE RIVERA
METHANE-Barrier 7/10/2020 Approved FREDDIE RIVERA
METHANE-Subgrade 7/10/2020 Approved FREDDIE RIVERA
Wood Frame 7/20/2020 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/1/2020 Approved FREDDIE RIVERA
ELECTRICAL-Final 12/1/2020 Approved FREDDIE RIVERA
Final 12/1/2020 Corrections Issued FREDDIE RIVERA
Green Building Final 12/1/2020 Approved FREDDIE RIVERA
Green Building Rough 12/1/2020 Approved FREDDIE RIVERA
HVAC-Final 12/1/2020 Approved FREDDIE RIVERA
METHANE-Final 12/1/2020 Approved FREDDIE RIVERA
METHANE-Rough 12/1/2020 Approved FREDDIE RIVERA
PLUMBING-Final 12/1/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 12/1/2020 SGSOV Not Required FREDDIE RIVERA
Service/Power Release 12/1/2020 Not Required FREDDIE RIVERA
Smoke Detectors 12/1/2020 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 12/1/2020 Approved FREDDIE RIVERA
Final 1/13/2021 Not Ready for Inspection FREDDIE RIVERA