1935 W 81ST ST 90047
Certificate Information: 1935 W 81ST ST 90047
- Application / Permit
- 20016-10000-12130
- Plan Check / Job No.
- B20LA09120
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Supplemental to permit #19010-30000-05082 to update structural inventory and revise scope of work to:New Accessory Dwelling Unit over raised floor foundation. RADCO Approved Factory Built Housing Unit Per: RAD-31-1027 & RAD-31-1028
- Permit Issued
- Issued on 7/7/2020
- Issuing Office
- Current Status
- Permit Finaled on 2/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2020 | LAMAR DAVIS |
| Corrections Issued | 5/28/2020 | LAMAR DAVIS |
| Quality Review Completed | 6/8/2020 | TU HUA |
| Plan Check Approved | 6/26/2020 | LAMAR DAVIS |
| Issued | 7/7/2020 | APPLICANT |
| Permit Finaled | 1/12/2021 | FREDDIE RIVERA |
| CofO in Progress | 2/9/2021 | FREDDIE RIVERA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/9/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Modative Build Inc; Lic. No.: 957698-B | 8757 WASHINGTON BLVD CULVER CITY, CA 90232 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/9/2020 | Approved | FREDDIE RIVERA |
| Wood Frame | 7/17/2020 | Partial Approval | FREDDIE RIVERA |
| Wood Frame | 7/23/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 11/12/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/1/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 12/1/2020 | Approved | FREDDIE RIVERA |
| Final | 12/1/2020 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 12/1/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/1/2020 | Approved | FREDDIE RIVERA |
| HVAC-Final | 12/1/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 12/1/2020 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 12/1/2020 | SGSOV Not Required | FREDDIE RIVERA |
| Service/Power Release | 12/1/2020 | Not Required | FREDDIE RIVERA |
| Smoke Detectors | 12/1/2020 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 12/1/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/24/2020 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 12/24/2020 | Corrections Issued | FREDDIE RIVERA |
| Final | 1/12/2021 | Permit Finaled | FREDDIE RIVERA |
| Final | 2/8/2021 | OK to Issue CofO | FREDDIE RIVERA |