400 S HOPE ST 7th FL 90071

Certificate Information: 400 S HOPE ST 7th FL 90071

Application / Permit
20016-10000-12110
Plan Check / Job No.
B20LA09114
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
TENANT IMPROVEMENT TO THE EXISTING 7TH FLR OFFICE. NEW NON-STRUCUTRAL PARTITIONS, CEILINGS, LIGHT FIXTURES, AND FINISHES.
Permit Issued
Issued on 11/6/2020
Issuing Office
Current Status
Permit Finaled on 6/7/2021

Permit Application Status History

Submitted 5/20/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 SAMUEL GONZALEZ
Corrections Issued 6/23/2020 SAMUEL GONZALEZ
Quality Review Completed 6/25/2020 LAWRENCE QUIRANTE
Disabled Access Plans Picked Up 6/29/2020 APPLICANT
Green Plans Picked Up 9/17/2020 APPLICANT
Plan Check Approved 10/29/2020 SAMUEL GONZALEZ
Issued 11/6/2020 APPLICANT
Building Plans Picked Up 11/6/2020 APPLICANT
Permit Finaled 6/4/2021 KATY RAMIREZ

Permit Application Clearance Information

Sewer availability Cleared 7/15/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 7/20/2020 EMIL KYUPELYAN
Fire Marshall Fire Life Safety Cleared 7/23/2020 OSCAR SALGADO JR
Green Code Cleared 7/27/2020 VIVIAN LAO
DAS Clearance Cleared 9/9/2020 SAMUEL GONZALEZ

Contact Information

Architect Herst,, Hans Robert; Lic. No.: C12001 500 S FIGUEROA AVENUE      LOS ANGELES, CA 90071
Contractor Howard Building Corporation; Lic. No.: 445804-B 707 WILSHIRE BLVD STE 3750      LOS ANGELES, CA 90017
Engineer Caravalho,, Kim Marie; Lic. No.: S4896 541 LINWOOD AVENUE UNIT A      MONROVIA, CA 91016

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 11/25/2020 Approved DANIEL COLLINS
Light Gage Steel Frame 11/25/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/14/2020 No Access for Inspection KATY RAMIREZ
Light Gage Steel Frame 12/15/2020 Partial Approval KATY RAMIREZ
Insulation 12/18/2020 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 1/25/2021 Partial Approval RONALD PACHECO
Drywall Nailing 1/29/2021 Corrections Issued KATY RAMIREZ
Special/Order Compliance 2/2/2021 Corrections Issued KATY RAMIREZ
Insulation 2/8/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/8/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 2/19/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/19/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/22/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 3/2/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 3/2/2021 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 3/8/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 3/8/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 3/23/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 4/1/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 4/6/2021 Not Ready for Inspection KATY RAMIREZ
T-Bar Ceiling 4/6/2021 Partial Approval KATY RAMIREZ
Special/Order Compliance 4/8/2021 Partial Approval KATY RAMIREZ
Special/Order Compliance 5/27/2021 Partial Approval DANIEL COLLINS
Special/Order Compliance 6/3/2021 Not Ready for Inspection KATY RAMIREZ
Final 6/4/2021 Permit Finaled KATY RAMIREZ
Green Building Final 6/4/2021 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 6/4/2021 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 6/4/2021 Approved KATY RAMIREZ