4021 1/2 S VAN NESS AVE 90062

Certificate Information: 4021 1/2 S VAN NESS AVE 90062

Application / Permit
20016-10000-12094
Plan Check / Job No.
B20LA09097
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF (E) GARAGE, (487 SF) TO (N) ADU PER CA GOVT CODE 65852.2(e)(1)(A)
Permit Issued
Issued on 6/26/2021
Issuing Office
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2020 APPLICANT
Assigned to Plan Check Engineer 6/2/2020 ADAM HEGAZI
Corrections Issued 6/2/2020 ADAM HEGAZI
Applicant returned to address corrections 4/13/2021 SAMUEL GONZALEZ
Plan Check Approved 6/16/2021 ADAM HEGAZI
Building Plans Picked Up 6/18/2021 APPLICANT
Issued 6/26/2021 APPLICANT
CofO in Progress 12/13/2021 ANTHONY EGSON
Permit Finaled 1/29/2022 DEROLD HAUFF
CofO Issued 1/29/2022 DEROLD HAUFF
Permit Finaled 1/29/2022 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 4/13/2021 JOHN BACON
ZA Case Cleared 4/22/2021 RUBEN VASQUEZ
Address approval Cleared 4/30/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 4/30/2021 ROSA SILVA
Sewer availability Cleared 4/30/2021 ROSA SILVA
Hydrant and Access approval Cleared 5/27/2021 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/22/2021 Corrections Issued ASHLEY THOMPSON
Underground Mechanical 7/22/2021 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 7/23/2021 Corrections Issued DAVID FEILER
Gas Test 7/23/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 7/23/2021 Partial Inspection DAVID FEILER
Footing/Foundation/Slab 7/27/2021 Partial Approval DAVID FEILER
Deputy Drilled-In Anchors 8/5/2021 Approved DAVID FEILER
Footing/Foundation/Slab 8/5/2021 Approved DAVID FEILER
Underground Mechanical 8/5/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 8/25/2021 Partial Inspection DAVID FEILER
ELECTRICAL-Rough 9/21/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 9/21/2021 Not Ready for Inspection DAVID FEILER
Rough-Elec/Plmb/HVAC 9/21/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 9/27/2021 Partial Approval DAVID FEILER
ELECTRICAL-Rough 9/27/2021 Approved DAVID FEILER
HVAC-Rough 9/27/2021 Approved DAVID FEILER
PLUMBING-Rough 9/27/2021 Approved DAVID FEILER
BUILDING-Rough-Frame 10/1/2021 Approved CALEB MEISTER
Drywall Nailing 10/1/2021 Approved CALEB MEISTER
Insulation 10/1/2021 Approved CALEB MEISTER
Interior/Exterior Lathing 10/1/2021 Partial Approval CALEB MEISTER
Interior/Exterior Lathing 10/5/2021 Approved RUBEN SALAS
Interior/Exterior Lathing 10/6/2021 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/12/2021 Approved ALIZAH MAYAGOITIA
Final 10/29/2021 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Approved ANTHONY EGSON
Smoke Detectors 10/29/2021 Approved ANTHONY EGSON
Final 11/4/2021 Corrections Issued ANTHONY EGSON
Final 11/12/2021 Partial Approval ANTHONY EGSON