5210 N ALLOTT AVE 91401
Certificate Information: 5210 N ALLOTT AVE 91401
- Application / Permit
- 20016-10000-12041
- Plan Check / Job No.
- B20LA09063
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING STORAGE ROOM TO ADU.
- Permit Issued
- Issued on 6/25/2020
- Issuing Office
- Current Status
- CofO Issued on 5/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2020 | JOE VO |
| Corrections Issued | 5/28/2020 | JOE VO |
| Quality Review Completed | 6/5/2020 | PRANITA SHAH |
| Plan Check Approved | 6/17/2020 | JOE VO |
| Issued | 6/25/2020 | APPLICANT |
| CofO in Progress | 2/25/2021 | ARAM AVEDISIAN |
| CofO Issued | 5/8/2021 | MICHAEL SMITH |
| Permit Finaled | 5/8/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 6/15/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 6/17/2020 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: NA72927 | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/24/2020 | Corrections Issued | BEAU COLLINS |
| Footing/Foundation/Slab | 7/30/2020 | Corrections Issued | CHARLES POWELL |
| Underground Mechanical | 7/30/2020 | Approved | CHARLES POWELL |
| Deputy Drilled-In Anchors | 7/31/2020 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 8/5/2020 | Approved | CHARLES POWELL |
| Underground Mechanical | 8/5/2020 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 9/2/2020 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 9/2/2020 | Corrections Issued | DANIEL DREW |
| Green Building Rough | 9/2/2020 | Approved | DANIEL DREW |
| HVAC-Rough | 9/2/2020 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 9/2/2020 | Corrections Issued | DANIEL DREW |
| Wood Frame | 9/2/2020 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 9/8/2020 | Partial Approval | CHARLES POWELL |
| HVAC-Rough | 9/8/2020 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 9/8/2020 | Approved | CHARLES POWELL |
| Wood Frame | 9/8/2020 | Partial Approval | CHARLES POWELL |
| Wood Frame | 9/11/2020 | Approved | CHARLES POWELL |
| Insulation | 9/15/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 9/15/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 9/18/2020 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 1/8/2021 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 1/8/2021 | Partial Inspection | THOMAS FINNILA |
| HVAC-Final | 1/8/2021 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 1/8/2021 | Partial Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/9/2021 | Approved | THOMAS FINNILA |
| Final | 2/9/2021 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/9/2021 | Partial Inspection | THOMAS FINNILA |
| Green Building Final | 2/9/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Final | 2/25/2021 | Approved | ARAM AVEDISIAN |
| Final | 2/25/2021 | OK to Issue CofO | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 2/25/2021 | Approved | ARAM AVEDISIAN |
| Green Building Final | 2/25/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 2/25/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 2/25/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 2/25/2021 | Approved | ARAM AVEDISIAN |