3053 S FARMDALE AVE 90016
Certificate Information: 3053 S FARMDALE AVE 90016
- Application / Permit
- 20016-10000-12016
- Plan Check / Job No.
- B20LA09044
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE/RUMPUS ROOM TO ACCESSOR DWELLING UNIT. DEMOLISH ATTACHED PATIO.
- Permit Issued
- Issued on 12/17/2020
- Issuing Office
- Current Status
- CofO Issued on 7/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 5/26/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 11/13/2020 | LUKE GONZALES |
| Plan Check Approved | 12/13/2020 | GEORGE ALVAREZ |
| Issued | 12/17/2020 | APPLICANT |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| CofO in Progress | 7/9/2021 | STUART CHAPMAN |
| Permit Finaled | 7/21/2021 | DEROLD HAUFF |
| CofO Issued | 7/21/2021 | DEROLD HAUFF |
| Permit Finaled | 7/21/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/16/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/16/2020 | WALTER RAMIREZ |
| Address approval | Cleared | 10/30/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2020 | RENZ SORIANO |
| Permit | Cleared | 10/30/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 10/30/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 10/30/2020 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/18/2020 | No Result Entered | CHARLENE BUSTAMANTE |
| FLOOD-Elevation Certificate | 12/23/2020 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/23/2020 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 12/23/2020 | Corrections Issued | STUART CHAPMAN |
| Underground Mechanical | 12/23/2020 | Partial Approval | STUART CHAPMAN |
| Special/Order Compliance | 12/29/2020 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2021 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 2/8/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/8/2021 | Approved | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 2/8/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 2/8/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 2/8/2021 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 2/8/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/17/2021 | Approved | STUART CHAPMAN |
| Insulation | 2/19/2021 | Approved | STUART CHAPMAN |
| Drywall Nailing | 3/4/2021 | Approved | STUART CHAPMAN |
| Sewer | 3/4/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 3/4/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Gas Test | 4/20/2021 | Approved | STUART CHAPMAN |
| Sewer | 4/20/2021 | Approved | STUART CHAPMAN |
| Underground Mechanical | 4/20/2021 | Approved | STUART CHAPMAN |
| Verify Rec and Parks Fee Memo | 4/20/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/4/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 6/4/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 6/4/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Final | 6/4/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 6/4/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 6/4/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 6/4/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 6/4/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 6/11/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 6/11/2021 | Approved | STUART CHAPMAN |
| Final | 6/11/2021 | Conditional Approval | STUART CHAPMAN |
| HVAC-Final | 6/11/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 6/11/2021 | Approved | STUART CHAPMAN |
| Verify Rec and Parks Fee Memo | 6/11/2021 | Approved | STUART CHAPMAN |
| Service/Power Release | 7/21/2021 | Not Ready for Inspection | RUBEN SALAS |