3546 N COPELAND PL 90032
Certificate Information: 3546 N COPELAND PL 90032
- Application / Permit
- 20016-10000-11783
- Plan Check / Job No.
- B20LA08896
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2 CAR GARAGE INTO AN ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Current Status
- CofO Issued on 9/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2020 | CRISTINA SALAZAR |
| Corrections Issued | 5/19/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 8/14/2020 | AMIR DANAI |
| Applicant returned to address corrections | 12/18/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 12/21/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 12/21/2020 | RAHEL BEYENE |
| Issued | 4/12/2021 | APPLICANT |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| CofO in Progress | 9/3/2022 | AMY COLIN |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| CofO Issued | 9/16/2022 | DEROLD HAUFF |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 6/9/2020 | ANNA VIDAL |
| Grading Pre-Inspection | Cleared | 6/11/2020 | PATRICK MISCHLICH |
| Address approval | Cleared | 6/15/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/20/2021 | Approved | COREY HUPP |
| Sewer | 5/20/2021 | Approved | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 6/18/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/19/2021 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 7/19/2021 | Corrections Issued | COREY HUPP |
| Underground Mechanical | 7/19/2021 | Corrections Issued | COREY HUPP |
| BUILDING-Rough-Frame | 7/26/2021 | Partial Approval | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 7/26/2021 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 8/6/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 8/6/2021 | Corrections Issued | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 8/6/2021 | Partial Approval | COREY HUPP |
| HVAC-Rough | 8/9/2021 | Approved | COREY HUPP |
| Insulation | 8/18/2021 | Not Ready for Inspection | COREY HUPP |
| Insulation | 8/23/2021 | Approved | COREY HUPP |
| Drywall Nailing | 8/25/2021 | Approved | COREY HUPP |
| ELECTRICAL-Final | 7/25/2022 | Corrections Issued | AMY COLIN |
| Gas Test | 7/25/2022 | Approved | AMY COLIN |
| Green Building Final | 7/25/2022 | Corrections Issued | AMY COLIN |
| HVAC-Final | 7/25/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 7/25/2022 | Approved | AMY COLIN |
| Final | 7/28/2022 | Not Ready for Inspection | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 7/28/2022 | SGSOV Not Ready | AMY COLIN |
| Smoke Detectors | 7/28/2022 | Not Ready for Inspection | AMY COLIN |
| Final | 8/5/2022 | Corrections Issued | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 8/5/2022 | SGSOV Not Ready | AMY COLIN |
| Smoke Detectors | 8/5/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 8/10/2022 | SGSOV Approved | AMY COLIN |
| ELECTRICAL-Final | 8/16/2022 | Approved | AMY COLIN |
| Final | 8/16/2022 | Partial Inspection | AMY COLIN |
| Final | 9/3/2022 | OK to Issue CofO | AMY COLIN |
| Service/Power Release | 9/3/2022 | Approved | AMY COLIN |