1835 S VICTORIA AVE 90019
Certificate Information: 1835 S VICTORIA AVE 90019
- Application / Permit
- 20016-10000-11778
- Plan Check / Job No.
- B20LA08890
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF (E) DETACHED GARAGE AND NEW 2ND STORY ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). NEW GROUND FLOOR ADDITION TO GARAGE. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 9/22/2021
- Issuing Office
- Current Status
- CofO Issued on 5/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | KEVIN MORALES |
| Corrections Issued | 12/23/2020 | KEVIN MORALES |
| Quality Review Completed | 12/23/2020 | EUGENE BARBEAU |
| Applicant returned to address corrections | 4/8/2021 | KEVIN MORALES |
| Plan Check Approved | 9/22/2021 | KEVIN MORALES |
| Issued | 9/22/2021 | APPLICANT |
| Building Plans Picked Up | 9/23/2021 | APPLICANT |
| CofO in Progress | 4/20/2023 | MICHAEL LEWIS |
| Permit Finaled | 5/13/2023 | DEROLD HAUFF |
| CofO Issued | 5/13/2023 | DEROLD HAUFF |
| Permit Finaled | 5/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 3/1/2021 | LAMBERT GIESSINGER |
| HPOZ | Cleared | 3/1/2021 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 3/1/2021 | LAMBERT GIESSINGER |
| Address approval | Cleared | 4/6/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | JEANIE LAM |
| Sewer availability | Cleared | 9/15/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/20/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/18/2021 | Partial Approval | STUART CHAPMAN |
| Pre-Inspection | 10/18/2021 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 11/5/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/5/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Structural Steel Frame | 11/5/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 11/15/2021 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/15/2021 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/3/2022 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 5/3/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 5/3/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 5/3/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 5/3/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/8/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/8/2022 | Approved | STUART CHAPMAN |
| Gas Test | 7/8/2022 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 7/8/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 7/8/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 7/8/2022 | Approved | STUART CHAPMAN |
| Insulation | 7/13/2022 | Corrections Issued | STUART CHAPMAN |
| Drywall Nailing | 8/1/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/1/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 8/1/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 8/1/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/8/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/8/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/24/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 2/24/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 2/24/2023 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Final | 2/24/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 2/24/2023 | SGSOV Not Ready | CALEB MEISTER |
| Smoke Detectors | 2/24/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/16/2023 | Approved | CALEB MEISTER |
| Final | 3/16/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 3/16/2023 | Approved | CALEB MEISTER |
| METHANE-Final | 3/16/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 3/16/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 3/16/2023 | Approved | CALEB MEISTER |
| Final | 4/19/2023 | OK to Issue CofO | MICHAEL LEWIS |