3637 W 60TH ST 90043
Certificate Information: 3637 W 60TH ST 90043
- Application / Permit
- 20016-10000-11740
- Plan Check / Job No.
- B20LA08851
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage and 2nd floor addition to accessory dwelling unit (ADU).
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- CofO Corrected on 2/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2020 | JOE VO |
| Corrections Issued | 5/28/2020 | JOE VO |
| Quality Review Completed | 6/5/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 7/15/2020 | JOE VO |
| Plan Check Approved | 7/16/2020 | JOE VO |
| Issued | 8/19/2020 | APPLICANT |
| CofO in Progress | 10/28/2021 | FREDDIE RIVERA |
| CofO Issued-Status Void | 1/22/2022 | DEROLD HAUFF |
| Permit Finaled-Status Void | 1/22/2022 | DEROLD HAUFF |
| Re-Activate Permit | 2/2/2022 | DEROLD HAUFF |
| Permit Finaled | 2/2/2022 | DEROLD HAUFF |
| CofO Corrected | 2/2/2022 | DEROLD HAUFF |
| Permit Finaled | 2/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 7/7/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/7/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/2/2020 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/14/2020 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/29/2020 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 10/29/2020 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 10/29/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 10/29/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/14/2020 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/14/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 12/14/2020 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/17/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/17/2020 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 12/17/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 12/17/2020 | Approved | FREDDIE RIVERA |
| Insulation | 12/23/2020 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 12/30/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 3/26/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 3/26/2021 | Approved | FREDDIE RIVERA |
| Sewer | 3/26/2021 | Approved | FREDDIE RIVERA |
| Gas Test | 4/12/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Final | 10/19/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 10/19/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/19/2021 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 10/19/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 10/27/2021 | OK to Issue CofO | FREDDIE RIVERA |
| Smoke Detectors | 10/27/2021 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 11/30/2021 | Corrections Issued | FREDDIE RIVERA |
| Service/Power Release | 11/30/2021 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 12/9/2021 | Approved | FREDDIE RIVERA |