2204 S STRONG'S DR 90291
Certificate Information: 2204 S STRONG'S DR 90291
- Application / Permit
- 20016-10000-11734
- Plan Check / Job No.
- B20LA08833
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (5) SSCC.
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- CofC Issued on 4/18/2022
Permit Application Status History
| Submitted | 5/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | JESSE VIDUYA |
| Corrections Issued | 6/25/2020 | JESSE VIDUYA |
| Quality Review Completed | 6/29/2020 | SAI KHUM |
| Building Plans Picked Up | 7/7/2020 | APPLICANT |
| Plan Check Approved | 8/21/2020 | JESSE VIDUYA |
| Issued | 10/20/2020 | APPLICANT |
| OK for CofC | 4/18/2022 | GRANT WOODS |
| CofC Issued | 4/18/2022 | DAVID TSAU |
Permit Application Clearance Information
| Work Adjacent to Public Way | Cleared | 7/20/2020 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2020 | SAUL GARCIA |
| Tenant Habitability Plan | Cleared | 10/15/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 1626 S MAYFLOWER AVE UNIT B MONROVIA, CA 91016 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/13/2020 | Approved | GRANT WOODS |
| Wood Frame | 11/20/2020 | Partial Inspection | GRANT WOODS |
| Deputy Drilled-In Anchors | 11/24/2020 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 12/1/2020 | Approved | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 12/1/2020 | Approved | SORIN CIRSTOIU |
| Wood Frame | 12/1/2020 | Partial Approval | SORIN CIRSTOIU |
| Wood Frame | 12/11/2020 | Partial Approval | GRANT WOODS |
| Interior/Exterior Lathing | 6/18/2021 | Approved | GRANT WOODS |
| Final | 12/10/2021 | Conditional Approval | JONATHAN ALLEN |
| METHANE-Final | 12/10/2021 | Approved | JONATHAN ALLEN |
| SGSOV-Seismic Gas S/O Valve | 12/10/2021 | SGSOV Approved | JONATHAN ALLEN |
| Smoke Detectors | 12/10/2021 | Approved | JONATHAN ALLEN |
| Final | 4/18/2022 | OK for CofC | GRANT WOODS |