4324 W JEFFERSON BLVD 90016
Certificate Information: 4324 W JEFFERSON BLVD 90016
- Application / Permit
- 20016-10000-11689
- Plan Check / Job No.
- B20LA08806
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- 1ST FLOOR TENANT IMPROVEMENT WITH SQUARE FOOTAGEOF 3,600 FOR RETAIL AND OFFICE AREA. SCOPE WILL INCLUDE BACK PARKING AREA RE-STRIPPING, FRONT WINDOW OPENING MODIFICATION AND EXTERIOR BLDG. REPAINTING
- Permit Issued
- Issued on 3/17/2021
- Issuing Office
- Current Status
- CofO Issued on 7/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 6/19/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 6/29/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 7/9/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 7/9/2020 | APPLICANT |
| Green Plans Picked Up | 7/9/2020 | APPLICANT |
| Applicant returned to address corrections | 8/6/2020 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 11/12/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 3/17/2021 | SERGIO GUTIERREZ |
| Issued | 3/17/2021 | APPLICANT |
| CofO in Progress | 7/14/2021 | TERRY HERR |
| CofO Issued | 7/14/2021 | TERRY HERR |
| Permit Finaled | 7/14/2021 | TERRY HERR |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 7/22/2020 | MICAELA TORRES-GIL |
| Community Plan Implem. Overlay | Cleared | 7/28/2020 | SAM NAVID |
| Sewer availability | Cleared | 7/28/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2020 | ELAINE LEI |
| Community Plan Implem. Overlay | Cleared | 8/12/2020 | TAIMOUR TANAVOLI |
| DAS Clearance | Cleared | 10/9/2020 | SHINE LIN |
| Green Code | Cleared | 10/18/2020 | VIVIAN LAO |
| Redevelopment Project Area | Cleared | 11/13/2020 | GRACIELA ACOSTA |
| ZI | Cleared | 11/13/2020 | GRACIELA ACOSTA |
| Flood clearance | Cleared | 2/10/2021 | RAYMOND LAM |
| Community Plan Implem. Overlay | Cleared | 2/25/2021 | KYLE WINSTON |
Contact Information
| Architect | Dwyer,, Mark Steven; Lic. No.: C23283 | 3244 BROAD STREET #A NEWPORT BEACH, CA 92663 |
| Contractor | Division 2 Construction Inc; Lic. No.: 986010-B | 120 INDUSTRIAL WAY COSTA MESA, CA 92627 |
| Engineer | Eimani,, Touraj; Lic. No.: S4302 | 12 MORNING LIGHT NEWPORT BEACH, CA 92657 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/23/2021 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 3/30/2021 | Approved | TIMOTHY BUXTON |
| Green Building Rough | 3/30/2021 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 3/30/2021 | Approved | TIMOTHY BUXTON |
| Wood Frame | 3/30/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 4/7/2021 | Conditional Approval | TIMOTHY BUXTON |
| Pre-Inspection | 4/23/2021 | Corrections Issued | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 4/29/2021 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 5/3/2021 | Conditional Approval | TIMOTHY BUXTON |
| Wood Frame | 5/3/2021 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 5/4/2021 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 5/7/2021 | Partial Approval | TIMOTHY BUXTON |
| Wood Frame | 5/14/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 5/18/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 5/20/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 5/20/2021 | Approved | LEOPOLDO MENDOZA |
| Drywall Nailing | 5/26/2021 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 6/11/2021 | Approved | TIMOTHY BUXTON |
| Final | 6/25/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 6/25/2021 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 6/25/2021 | Approved | TIMOTHY BUXTON |
| Final | 7/8/2021 | Conditional Approval | TIMOTHY BUXTON |
| Smoke Detectors | 7/8/2021 | Approved | TIMOTHY BUXTON |
| Wood Frame | 7/8/2021 | Approved | TIMOTHY BUXTON |
| Insulation | 7/13/2021 | Not Ready for Inspection | TIMOTHY BUXTON |