317 S BROADWAY 90013
Certificate Information: 317 S BROADWAY 90013
- Application / Permit
- 20016-10000-11673
- Plan Check / Job No.
- B20LA08786
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Dining Room public
- Work Description
- TI TO GRAND CENTRAL MARKET BASEMENT AREA WITH 4 NEW FOOD PREP AREAS AND JANITOR'S CLOSET TO SERVE TENANTS SPACES ON GROUND LEVEL. CHANGE OF USE OF AN AREA FORMERLY A SUNDRIES GENERAL STORE (M OCCUPANCY) TO AN EVENT SPACE AND OVERFLOW SEATING AREA FOR THE GROUND FLOOR ABOVE (A-2 OCCUPANCY). see comments
- Permit Issued
- Issued on 3/8/2022
- Issuing Office
- Current Status
- Issued on 3/8/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2020 | RAHEL BEYENE |
| Corrections Issued | 5/22/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 6/30/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 8/18/2021 | ADAM HEGAZI |
| Applicant returned to address corrections | 11/2/2021 | TSE MING HUANG |
| Plan Check Approved | 12/9/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 12/10/2021 | APPLICANT |
| Issued | 3/8/2022 | APPLICANT |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 6/9/2020 | LAMBERT GIESSINGER |
| ZA Case | Cleared | 6/18/2020 | RUBEN VASQUEZ |
| Redevelopment Project Area | Cleared | 6/19/2020 | DAVID URITA |
| Food Service Establishment | Cleared | 9/1/2021 | PAWAN VERMA |
| Fire Marshal Fire Life Safety | Cleared | 10/21/2021 | MENOA AGHAJANI |
| Historic monument | Cleared | 12/2/2021 | LAMBERT GIESSINGER |
Contact Information
| Architect | Levin,, Brenda A; Lic. No.: C11323 | 700 S FLOWER STREET SUITE 700 LOS ANGELES, CA 90017 |
| Contractor | Gillett Construction Services Inc; Lic. No.: 892160-B | 4859 W SLAUSON AVE #402 LOS ANGELES, CA 90056 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/16/2022 | Approved | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 4/14/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 4/14/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 5/18/2022 | Conditional Approval | TIMOTHY BUXTON |
| Structural Steel Frame | 5/25/2022 | Approved | TIMOTHY BUXTON |
| Wall Anchors | 5/25/2022 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 7/7/2022 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 9/6/2022 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 11/4/2022 | Partial Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 11/4/2022 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 11/10/2022 | Partial Approval | ALAN MORELOS |
| Drywall Nailing | 11/17/2022 | Partial Approval | TIMOTHY BUXTON |
| T-Bar Ceiling | 2/28/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Special/Order Compliance | 3/7/2023 | Corrections Issued | KATY RAMIREZ |
| T-Bar Ceiling | 4/20/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 5/31/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Reinforced Concrete Frame | 5/31/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Not Ready | LUIS CCAMACHO |
| Smoke Detectors | 5/31/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Pre-Inspection | 10/29/2025 | Not Ready for Inspection | PAUL BAZERKANIAN |