2069-2071 S LINNINGTON AVE 90025

Certificate Information: 2069-2071 S LINNINGTON AVE 90025

Application / Permit
20016-10000-11457
Plan Check / Job No.
B20LA08610
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF EXISTING LOWER LEVEL AND ATTACHED TWO CAR GARAGE TO A.D.U.
Permit Issued
Issued on 2/23/2021
Issuing Office
Current Status
CofO Issued on 1/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2020 APPLICANT
Assigned to Plan Check Engineer 5/15/2020 CHUNG-WEN CHUANG
Corrections Issued 5/15/2020 CHUNG-WEN CHUANG
Applicant returned to address corrections 7/13/2020 AUNG SOE
Applicant returned to address corrections 9/8/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 12/9/2020 CRISTINA SALAZAR
Applicant returned to address corrections 2/3/2021 SHANGQIN XIE
Building Plans Picked Up 2/5/2021 APPLICANT
Plan Check Approved 2/10/2021 RICARDO RAMIREZ
Issued 2/23/2021 APPLICANT
CofO in Progress 9/29/2023 STEPHANIE SWANSON
No Progress 12/2/2023 MICHAEL PELHAM
CofO in Progress 12/19/2023 STEPHANIE SWANSON
Permit Finaled 1/5/2024 DANIEL ORRANTE
CofO Issued 1/5/2024 DANIEL ORRANTE
Permit Finaled 1/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/1/2020 SAUL GARCIA
Sewer availability Cleared 9/1/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 9/2/2020 SAUL GARCIA
Miscellaneous Cleared 9/2/2020 SAUL GARCIA
Specific Plan Cleared 9/28/2020 VALERIA CEJA
Grading Pre-Inspection Cleared 11/16/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Shoraka,, Khojasteh Farhang; Lic. No.: C33555 1423 S BEVERLY GLEN UNIT A      LOS ANGELES, CA 90024

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/2/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 3/2/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 3/26/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 4/9/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 5/12/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Wood Frame 5/12/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 5/25/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 5/25/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 5/25/2021 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 5/25/2021 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 6/15/2021 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 6/22/2021 Approved ADAM ESCOTO
Final 5/25/2023 Corrections Issued BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 5/25/2023 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 5/25/2023 Approved BRENDAN LOONEY
Final 9/14/2023 Corrections Issued STEPHANIE SWANSON
Final 9/29/2023 OK to Issue CofO STEPHANIE SWANSON
Special/Order Compliance 10/11/2023 Corrections Issued STEPHANIE SWANSON
Special/Order Compliance 12/19/2023 Approved STEPHANIE SWANSON