853 E WARREN AVE 90291

Certificate Information: 853 E WARREN AVE 90291

Application / Permit
20016-10000-11408
Plan Check / Job No.
B20LA08556
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF SINGLE FAMILY DWELLING: DEMO WALLS; ADD WOOD BEAMS; DEMO CEILING GYP. RECONFIGURE BATHROOM WITH NEW PLUMBING FIXTURES. ADD NEW WINDOWS AND DOORS. ADD NEW DECORATIVE LIGHTS, OUTLETS AND SWITCHES, ADD WOOD DECKS.
Permit Issued
Issued on 7/20/2020
Issuing Office
Current Status
Permit Finaled on 11/2/2020

Permit Application Status History

Submitted 5/12/2020 APPLICANT
Assigned to Plan Check Engineer 5/13/2020 FARSHAD ALIMOHAMADI
Corrections Issued 5/14/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 5/27/2020 TSE MING HUANG
Plan Check Approved 7/7/2020 GEORGE ALVAREZ
Issued 7/20/2020 APPLICANT
Building Plans Picked Up 7/21/2020 APPLICANT
Permit Finaled 11/2/2020 DAVID HEINE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/29/2020 DINAH GARIN
Low Impact Development Cleared 6/12/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/2/2020 DINAH GARIN

Contact Information

Contractor Wynn Builders Inc; Lic. No.: 825806-B 409 N PACIFIC COAST HWY 511      REDONDO BEACH, CA 90277
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/28/2020 Approved DAVID HEINE
Footing/Foundation/Slab 8/11/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 8/19/2020 Partial Approval DAVID HEINE
PLUMBING-Rough 8/25/2020 Corrections Issued DAVID HEINE
ELECTRICAL-Rough 9/3/2020 Approved DAVID HEINE
HVAC-Rough 9/3/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 9/4/2020 Approved DAVID HEINE
Insulation 9/9/2020 Approved DAVID HEINE
Underground Mechanical 9/9/2020 Approved DAVID HEINE
Drywall Nailing 9/11/2020 Approved DAVID HEINE
Interior/Exterior Lathing 9/14/2020 Corrections Issued DAVID HEINE
Interior/Exterior Lathing 9/16/2020 Approved DAVID HEINE
ELECTRICAL-Final 10/21/2020 Approved DAVID HEINE
Final 10/29/2020 Corrections Issued DAVID HEINE
SGSOV-Seismic Gas S/O Valve 10/29/2020 SGSOV Approved DAVID HEINE
Smoke Detectors 10/29/2020 Approved DAVID HEINE
Final 11/2/2020 Permit Finaled DAVID HEINE
Service/Power Release 11/2/2020 Approved DAVID HEINE