5017 S FIGUEROA ST 90037
Certificate Information: 5017 S FIGUEROA ST 90037
- Application / Permit
- 20016-10000-11396
- Plan Check / Job No.
- B20LA08534
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN 4798 - Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (1) STEEL SPECIAL CANTILEVER COLUMN.
- Permit Issued
- Issued on 2/3/2021
- Issuing Office
- Current Status
- CofC Issued on 5/11/2021
Permit Application Status History
| Submitted | 5/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2020 | DANIEL SANJUAN |
| Corrections Issued | 6/25/2020 | DANIEL SANJUAN |
| Quality Review Completed | 6/26/2020 | SAI KHUM |
| Plan Check Approved | 1/19/2021 | DANIEL SANJUAN |
| Issued | 2/3/2021 | APPLICANT |
| OK for CofC | 4/26/2021 | MARK FERRARI |
| CofC Issued | 5/11/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 10/16/2020 | DALE WILLIAMS |
| Community Plan Implem. Overlay | Cleared | 10/16/2020 | DALE WILLIAMS |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2020 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 11/16/2020 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 11/16/2020 | RAFAEL FONTES |
| Historic Resource Verification | Cleared | 11/18/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 12/1/2020 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 2/3/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Action Construction Company; Lic. No.: 640072-B | 5533 SATSUMA AVENUE NORTH HOLLYWOOD, CA 91601 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2021 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/9/2021 | Approved | JOEY BUCHANAN |
| Wood Frame | 3/9/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 3/11/2021 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 3/30/2021 | Approved | JOEY BUCHANAN |
| Final | 4/14/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/14/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/14/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 4/22/2021 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 4/22/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 4/22/2021 | Approved | MARK FERRARI |
| Final | 4/26/2021 | OK for CofC | MARK FERRARI |