4878 N EAGLE ROCK BLVD 90041

Certificate Information: 4878 N EAGLE ROCK BLVD 90041

Application / Permit
20016-10000-11353
Plan Check / Job No.
B20LA08498
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(21) Theater
Work Description
PROPOSED TENANT IMPROVEMENT FOR AN EXISTING THEATER AND RETAIL SPACE, WORK INLCUDES ADDITION TO EXISTING MEZZANINE, INTERIOR DEMOLITION, INTERIOR PARTITIONS, NEW RESTROOMS, SUSPEND CEILINGS, AND MILLWORK
Permit Issued
Issued on 5/20/2021
Issuing Office
Current Status
CofO Issued on 6/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2020 APPLICANT
Assigned to Plan Check Engineer 5/28/2020 MICHAEL LOPEZ
Corrections Issued 6/4/2020 MICHAEL LOPEZ
Quality Review Completed 6/9/2020 QUAN NGHIEM
Building Plans Picked Up 6/18/2020 APPLICANT
Applicant returned to address corrections 6/23/2020 MICHAEL LOPEZ
Disabled Access Plans Picked Up 6/24/2020 APPLICANT
Applicant returned to address corrections 8/11/2020 MICHAEL LOPEZ
Applicant returned to address corrections 8/12/2020 MICHAEL LOPEZ
Applicant returned to address corrections 9/16/2020 MICHAEL LOPEZ
Green Plans Picked Up 3/1/2021 APPLICANT
Applicant returned to address corrections 4/17/2021 MICHAEL LOPEZ
Plan Check Approved 5/6/2021 MICHAEL LOPEZ
Issued 5/20/2021 APPLICANT
CofO in Progress 6/8/2023 ERNESTO CORRAL
CofO Issued 6/8/2023 ERNESTO CORRAL
Permit Finaled 6/8/2023 ERNESTO CORRAL

Permit Application Clearance Information

"Q" conditions Cleared 6/23/2020 KENTON TRINH
ZA Case Cleared 6/23/2020 KENTON TRINH
Grading Pre-Inspection Cleared 7/2/2020 KIRK LINKLATER
Sewer availability Cleared 7/6/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/7/2020 WALLIE JONG
Fire Marshall Fire Life Safety Cleared 7/15/2020 VIDAL GARCIA
Green Code Cleared 7/30/2020 KHEDER ALRAZAA
DAS Clearance Cleared 9/17/2020 MICHAEL LOPEZ
Food Service Establishment Cleared 1/25/2021 KENNETH BROWNE
Miscellaneous Cleared 1/26/2021 BRYANT WU
Comm Cor/Mini-Mall Cleared 2/17/2021 BRYANT WU
Food establishment approval Cleared 4/19/2021 LACDHS APPROVED
ZA Case Cleared 5/4/2021 BRYANT WU

Contact Information

Architect Wick,, David Sochu; Lic. No.: C29199 2101 PARK DRIVE      LOS ANGELES, CA 90026
Contractor Analog Construction; Lic. No.: 1058496-B 1910 W SUNSET BLVD #660      LOS ANGELES, CA 90026
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/20/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/21/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 10/13/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 1/10/2022 Partial Approval MARK FERRARI
Footing/Foundation/Slab 3/2/2022 Partial Approval MARK FERRARI
Footing/Foundation/Slab 3/21/2022 Partial Approval MARK FERRARI
Special/Order Compliance 3/21/2022 Corrections Issued MARK FERRARI
Deputy Wood Construction 9/8/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 9/9/2022 Approved MARK FERRARI
Insulation 9/9/2022 Approved MARK FERRARI
Light Gage Steel Frame 9/9/2022 Corrections Issued MARK FERRARI
Structural Steel Frame 9/9/2022 Approved MARK FERRARI
Wall Anchors 9/9/2022 Approved MARK FERRARI
Wood Frame 9/9/2022 Corrections Issued MARK FERRARI
Drywall Nailing 9/26/2022 Partial Approval MARK FERRARI
Light Gage Steel Frame 10/27/2022 Not Ready for Inspection MARK FERRARI
Light Gage Steel Frame 10/31/2022 Corrections Issued MARK FERRARI
Wood Frame 12/1/2022 Approved MARK FERRARI
Drywall Nailing 12/8/2022 Approved MARK FERRARI
Final 5/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 5/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Rough 5/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Final 5/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
METHANE-Rough 5/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
Reinforced Masonry Frame 5/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 5/19/2023 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 5/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
Final 5/30/2023 Not Ready for Inspection RAFAEL CORTES
Green Building Final 5/30/2023 No Access for Inspection RAFAEL CORTES
Green Building Rough 5/30/2023 Approved RAFAEL CORTES
METHANE-Final 5/30/2023 Approved RAFAEL CORTES
METHANE-Rough 5/30/2023 Approved RAFAEL CORTES
Reinforced Masonry Frame 5/30/2023 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 5/30/2023 SGSOV Approved RAFAEL CORTES
Smoke Detectors 5/30/2023 Approved RAFAEL CORTES
Final 6/2/2023 OK to Issue CofO RONALD JIMENEZ
Green Building Final 6/2/2023 Approved RONALD JIMENEZ