1002 W CHILDS WAY 90089
Certificate Information: 1002 W CHILDS WAY 90089
- Application / Permit
- 20016-10000-11342
- Plan Check / Job No.
- B20LA08475
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Testing Laboratory
- Work Description
- TENANT IMPROVEMENT FOR NEW LAB IN EXISTING BUILDING INCLUDING SEISMIC ANCHORAGE FOR NEW EQUIPMENT
- Permit Issued
- Issued on 10/8/2020
- Issuing Office
- Current Status
- Permit Finaled on 4/7/2021
Permit Application Status History
| Submitted | 5/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 6/2/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 6/18/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 6/23/2020 | APPLICANT |
| Applicant returned to address corrections | 7/6/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 7/28/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 8/3/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/8/2020 | ARSALAN SHABESTARI |
| Issued | 10/8/2020 | APPLICANT |
| Permit Finaled | 4/7/2021 | DANIEL COLLINS |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/2/2020 | KYLE WINSTON |
| DAS Clearance | Cleared | 9/25/2020 | SOMKIAT SUPANYACHOTSKUL |
Contact Information
| Contractor | Penta Building Group The Llc; Lic. No.: 972201-B | 181 E WARM SPRINGS ROAD LAS VEGAS, NV 89119 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/16/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 10/21/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 10/23/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 10/29/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 10/30/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 11/2/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Structural Steel Frame | 11/4/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 11/12/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Drilled-In Anchors | 11/13/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Drilled-In Anchors | 11/17/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 11/17/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 11/30/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 12/4/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 12/8/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 12/10/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 12/16/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Deputy Other (see comments) | 12/18/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 12/18/2020 | Conditional Approval | LANNY MERRICK |
| Pre-Inspection | 1/5/2021 | Partial Inspection | LEOPOLDO MENDOZA |
| Reinforced Concrete Frame | 1/8/2021 | Approved | LEOPOLDO MENDOZA |
| Deputy Wood Construction | 2/8/2021 | Conditional Approval | DANIEL COLLINS |
| T-Bar Ceiling | 3/4/2021 | Approved | LANNY MERRICK |
| T-Bar Ceiling | 3/5/2021 | Approved | LANNY MERRICK |
| Final | 4/7/2021 | Permit Finaled | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 4/7/2021 | SGSOV Approved | DANIEL COLLINS |
| Smoke Detectors | 4/7/2021 | Approved | DANIEL COLLINS |