423 N HARVARD BLVD 90004

Certificate Information: 423 N HARVARD BLVD 90004

Application / Permit
20016-10000-11197
Plan Check / Job No.
B20LA08366
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story Seismic Retrofit per LABC Chapter 93: INSTALL STEEL CANTILEVER COLUMNS AND PLYWOOD SHEAR WALLS.
Permit Issued
Issued on 1/6/2021
Issuing Office
Current Status
CofC Issued on 5/24/2021

Permit Application Status History

Submitted 5/7/2020 APPLICANT
Assigned to Plan Check Engineer 5/20/2020 HANS SANTIAGO
Corrections Issued 5/26/2020 HANS SANTIAGO
Quality Review Completed 5/29/2020 SAI KHUM
Applicant returned to address corrections 8/3/2020 HANS SANTIAGO
Applicant returned to address corrections 8/18/2020 HANS SANTIAGO
Plan Check Approved 8/21/2020 ANDREW SANTIAGO
Issued 1/6/2021 APPLICANT
OK for CofC 5/20/2021 MARK FERRARI
CofC Issued 5/24/2021 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 11/23/2020 MICHAEL GREGERSON

Contact Information

Contractor Owner-Builder       ,
Engineer Sadjadi,, Abdulreza; Lic. No.: C51812 1223 WILSHIRE BLVD #169      SANTA MONICA, CA 90403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2021 Partial Approval JONATHAN QUACH
Special/Order Compliance 3/2/2021 Corrections Issued MARK FERRARI
Wood Frame 3/2/2021 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 3/15/2021 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 3/15/2021 Partial Inspection JONATHAN QUACH
Wood Frame 3/15/2021 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 3/16/2021 Approved JONATHAN QUACH
Wood Frame 3/16/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 3/18/2021 Conditional Approval JONATHAN QUACH
Wood Frame 3/24/2021 Conditional Approval JONATHAN QUACH
Deputy Wood Construction 3/26/2021 Conditional Approval MARK FERRARI
Structural Steel Frame 3/31/2021 Approved MARK FERRARI
Wood Frame 3/31/2021 Partial Approval MARK FERRARI
Wood Frame 4/6/2021 Approved JONATHAN QUACH
Interior/Exterior Lathing 4/12/2021 Partial Approval JONATHAN QUACH
Drywall Nailing 4/15/2021 Approved JONATHAN QUACH
Final 4/29/2021 Conditional Approval JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 4/29/2021 SGSOV Approved JONATHAN QUACH
Smoke Detectors 4/29/2021 Approved JONATHAN QUACH
Final 5/20/2021 OK for CofC MARK FERRARI