207 S LORRAINE BLVD 90004

Certificate Information: 207 S LORRAINE BLVD 90004

Application / Permit
20016-10000-11184
Plan Check / Job No.
B20LA08358
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
10'x6' addition to existing 1-story garage and convert it accessory dwelling unit.
Permit Issued
Issued on 9/30/2020
Issuing Office
Current Status
CofO Issued on 2/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2020 APPLICANT
Assigned to Plan Check Engineer 5/28/2020 CRYSTEL MAALOUF
Corrections Issued 6/10/2020 CRYSTEL MAALOUF
Quality Review Completed 7/22/2020 TU HUA
Applicant returned to address corrections 9/16/2020 CRYSTEL MAALOUF
Plan Check Approved 9/30/2020 CRYSTEL MAALOUF
Issued 9/30/2020 APPLICANT
CofO in Progress 9/19/2022 JEFFREY MEAD
Permit Finaled 2/22/2023 DANIEL ORRANTE
CofO Issued 2/22/2023 DANIEL ORRANTE
Permit Finaled 2/22/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/22/2020 ELAINE LEI
Roof/Waste drainage to street Cleared 6/22/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 6/23/2020 ELAINE LEI
Sewer availability Cleared 7/1/2020 ELAINE LEI
Construction within easement Cleared 7/4/2020 WALTER RAMIREZ
HPOZ Cleared 7/20/2020 LYDIA CHAPMAN
ZI Cleared 7/20/2020 LYDIA CHAPMAN
Green Code Cleared 9/30/2020 CRYSTEL MAALOUF

Contact Information

Contractor Alisal Builders Corp; Lic. No.: 732777-B P O BOX 6038      SAN PEDRO, CA 90734
Engineer Roth,, Jennifer Nicole; Lic. No.: C84889 110 THE VILLAGE UNIT 504      REDONDO BEACH, CA 90277

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/17/2021 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 3/1/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 3/1/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/10/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 5/10/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/10/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/17/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 5/17/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/21/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/27/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/27/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 5/27/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/27/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 6/21/2021 Approved JOSEPH MCGARRY
HVAC-Rough 7/1/2021 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/21/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 7/21/2021 Approved CHRIS CHRISTENSEN
Insulation 7/30/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/17/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/17/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/19/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 9/1/2021 Approved ARTHUR SARGSYAN
HVAC-Final 7/22/2022 Approved JEFFREY MEAD
PLUMBING-Final 7/22/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 8/1/2022 Approved JEFFREY MEAD
Final 9/16/2022 OK to Issue CofO JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved JEFFREY MEAD
Smoke Detectors 9/16/2022 Approved JEFFREY MEAD
Special/Order Compliance 12/19/2022 Corrections Issued JEFFREY MEAD