18398 W JOVAN ST 91335
Certificate Information: 18398 W JOVAN ST 91335
- Application / Permit
- 20016-10000-11148
- Plan Check / Job No.
- B20LA08327
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePLAN CHECK** CONVERSION OF (E) GARAGE & GROUND FLOOR ADDITION TO (N) ACCESSORY DWELLING UNIT PER CITY ORDINANCE
- Permit Issued
- Issued on 7/21/2020
- Issuing Office
- Current Status
- CofO Corrected on 7/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2020 | LAMAR DAVIS |
| Corrections Issued | 6/23/2020 | LAMAR DAVIS |
| Quality Review Completed | 7/2/2020 | TU HUA |
| Applicant returned to address corrections | 7/13/2020 | LAMAR DAVIS |
| Plan Check Approved | 7/17/2020 | LAMAR DAVIS |
| Issued | 7/21/2020 | APPLICANT |
| CofO in Progress | 7/2/2021 | STEVEN BACK |
| Re-Activate Permit | 7/28/2021 | JOHN JANSON |
| CofO Issued-Status Void | 7/28/2021 | JOHN JANSON |
| Permit Finaled-Status Void | 7/28/2021 | JOHN JANSON |
| Permit Finaled | 7/28/2021 | JOHN JANSON |
| CofO Corrected | 7/28/2021 | JOHN JANSON |
| Permit Finaled | 7/28/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/23/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/23/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/24/2020 | ADRIAN CASTRO |
| ZI | Cleared | 7/8/2020 | JOE LUCKEY |
| Construction near power lines | Cleared | 7/15/2020 | WALTER RAMIREZ |
| Construction within easement | Cleared | 7/15/2020 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wyatt,, Lars Wilton; Lic. No.: C85897 | 405 E 29TH ST APT 5 VANCOUVER, WA 98663 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/3/2020 | Partial Approval | STEVEN BACK |
| Sewer | 8/3/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 8/5/2020 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 8/5/2020 | Approved | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 8/7/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 8/7/2020 | Approved | STEVEN BACK |
| Pre-Inspection | 8/7/2020 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Partial Approval | STEVEN BACK |
| Green Building Rough | 9/4/2020 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 9/4/2020 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 9/8/2020 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 9/8/2020 | Approved | STEVEN BACK |
| Green Building Rough | 9/8/2020 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 9/8/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/18/2020 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2020 | Partial Inspection | STEVEN BACK |
| Green Building Rough | 9/18/2020 | Not Ready for Inspection | STEVEN BACK |
| Insulation | 9/18/2020 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 9/25/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2020 | Approved | STEVEN BACK |
| Green Building Rough | 9/25/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 9/25/2020 | Partial Approval | STEVEN BACK |
| Insulation | 10/14/2020 | Approved | STEVEN BACK |
| Shower Pan | 10/14/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 10/23/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 2/5/2021 | Corrections Issued | STEVEN BACK |
| Final | 2/5/2021 | Not Ready for Inspection | STEVEN BACK |
| Green Building Final | 2/5/2021 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Final | 2/5/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Final | 2/5/2021 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/5/2021 | SGSOV Not Ready | STEVEN BACK |
| Service/Power Release | 2/5/2021 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 2/5/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 2/9/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Final | 2/9/2021 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/9/2021 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 2/9/2021 | Approved | STEVEN BACK |
| Final | 4/1/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 4/1/2021 | Approved | VINCENT HANLEY |
| Final | 4/13/2021 | Corrections Issued | STEVEN BACK |
| Final | 6/29/2021 | Corrections Issued | STEVEN BACK |
| Final | 7/2/2021 | OK to Issue CofO | STEVEN BACK |