22734-22736 W BALTAR ST 91304

Certificate Information: 22734-22736 W BALTAR ST 91304

Application / Permit
20016-10000-11145
Plan Check / Job No.
B20LA08325
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*ePLAN CHECK* CONVERSION OF (E) GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT
Permit Issued
Issued on 8/13/2020
Issuing Office
Current Status
CofO Issued on 5/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 LAMAR DAVIS
Corrections Issued 5/15/2020 LAMAR DAVIS
Quality Review Completed 5/21/2020 TU HUA
Applicant returned to address corrections 6/2/2020 LAMAR DAVIS
Applicant returned to address corrections 6/17/2020 LAMAR DAVIS
Applicant returned to address corrections 7/13/2020 LAMAR DAVIS
Plan Check Approved 7/17/2020 LAMAR DAVIS
Issued 8/13/2020 APPLICANT
CofO in Progress 4/16/2021 DAVID STEPANYAN
No Progress 4/22/2021 DAVID STEPANYAN
CofO in Progress 5/5/2023 HORACE FULTZ
CofO in Progress 5/5/2023 HORACE FULTZ
Permit Finaled 5/5/2023 JOHN JANSON
CofO Issued 5/5/2023 JOHN JANSON
Permit Finaled 5/5/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/23/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 7/15/2020 GUILLERMO PETRA
Sewer availability Cleared 7/15/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/26/2020 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 9/23/2020 Partial Approval DAVID STEPANYAN
Sewer 9/23/2020 Approved DAVID STEPANYAN
Footing/Foundation/Slab 10/27/2020 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 11/5/2020 Approved DAVID STEPANYAN
ELECTRICAL-Rough 12/1/2020 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Approved DAVID STEPANYAN
HVAC-Rough 12/1/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 12/1/2020 Approved DAVID STEPANYAN
HVAC-Rough 12/3/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 12/7/2020 Approved DAVID STEPANYAN
Green Building Rough 12/7/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 12/7/2020 Partial Approval DAVID STEPANYAN
Insulation 12/14/2020 Corrections Issued JOSEPH SAGEN
Insulation 12/24/2020 Not Ready for Inspection DAVID STEPANYAN
Insulation 12/29/2020 No Access for Inspection DONALD SUNSERI
Insulation 1/11/2021 Approved DAVID STEPANYAN
Drywall Nailing 1/14/2021 Approved DAVID STEPANYAN
Shower Pan 1/26/2021 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 2/22/2021 SGSOV Not Required DAVID STEPANYAN
Final 3/10/2021 Corrections Issued DAVID STEPANYAN
Green Building Final 3/10/2021 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 3/10/2021 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 3/10/2021 Partial Approval DAVID STEPANYAN
Final 3/31/2021 Not Ready for Inspection DAVID STEPANYAN
Gas Test 3/31/2021 Approved DAVID STEPANYAN
HVAC-Final 3/31/2021 Approved DAVID STEPANYAN
PLUMBING-Final 3/31/2021 Approved DAVID STEPANYAN
Smoke Detectors 3/31/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Final 4/15/2021 Approved DAVID STEPANYAN
Final 4/15/2021 OK to Issue CofO DAVID STEPANYAN
Smoke Detectors 4/15/2021 Approved DAVID STEPANYAN
Special/Order Compliance 4/22/2021 Corrections Issued DAVID STEPANYAN