3124 E WABASH AVE 90063
Certificate Information: 3124 E WABASH AVE 90063
- Application / Permit
- 20016-10000-11114
- Plan Check / Job No.
- B20LA08305
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. USING OMF AND SCCS.
- Permit Issued
- Issued on 7/8/2021
- Issuing Office
- Current Status
- CofC Issued on 4/18/2022
Permit Application Status History
| Submitted | 5/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2020 | VARAND SARKISIAN |
| Corrections Issued | 6/9/2020 | VARAND SARKISIAN |
| Quality Review Completed | 6/10/2020 | SAI KHUM |
| Building Plans Picked Up | 7/14/2020 | APPLICANT |
| Applicant returned to address corrections | 9/3/2020 | VARAND SARKISIAN |
| Plan Check Approved | 10/29/2020 | VARAND SARKISIAN |
| Issued | 7/8/2021 | APPLICANT |
| OK for CofC | 4/15/2022 | BRUCE CAMPBELL |
| CofC Issued | 4/18/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 11/30/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Landome Inc; Lic. No.: 1040389-B | 7648 BECKETT ST TUJUNGA, CA 91042 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/20/2021 | Corrections Issued | MARK FERRARI |
| Special/Order Compliance | 8/20/2021 | Partial Inspection | MARK FERRARI |
| Deputy Steel/Welding | 9/7/2021 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 9/17/2021 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 9/20/2021 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 9/20/2021 | Not Ready for Inspection | MARK FERRARI |
| Structural Steel Frame | 9/20/2021 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 9/22/2021 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 9/22/2021 | Partial Approval | BRUCE CAMPBELL |
| Wood Frame | 10/1/2021 | Approved | BRUCE CAMPBELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Corrections Issued | MARK FERRARI |
| Structural Steel Frame | 1/6/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 1/6/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 1/19/2022 | Corrections Issued | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 1/21/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 2/1/2022 | Corrections Issued | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Not Ready | BRUCE CAMPBELL |
| Smoke Detectors | 2/1/2022 | Approved | BRUCE CAMPBELL |
| Final | 4/15/2022 | OK for CofC | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 4/15/2022 | SGSOV Approved | BRUCE CAMPBELL |