6065 W FOUNTAIN AVE 90028

Certificate Information: 6065 W FOUNTAIN AVE 90028

Application / Permit
20016-10000-11032
Plan Check / Job No.
B20LA08237
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Sound Stage
Work Description
STAGE 7 KITCHENETTE AND ELECTRICAL ROOM REMODEL. 2 OF 2
Permit Issued
Issued on 10/29/2020
Issuing Office
Current Status
Permit Finaled on 8/26/2021

Permit Application Status History

Submitted 5/12/2020 APPLICANT
Assigned to Plan Check Engineer 5/28/2020 JESSE ARELLANO
Disabled Access Plans Picked Up 6/15/2020 APPLICANT
Corrections Issued 7/10/2020 JESSE ARELLANO
Quality Review Completed 7/14/2020 OMID HEDAYAT
Applicant returned to address corrections 7/14/2020 JESSE ARELLANO
Applicant returned to address corrections 9/26/2020 JESSE ARELLANO
Plan Check Approved 10/14/2020 JESSE ARELLANO
Issued 10/29/2020 APPLICANT
Building Plans Picked Up 11/5/2020 APPLICANT
Permit Finaled 8/24/2021 RUSSELL BONVOULOIR

Permit Application Clearance Information

Historic Resource Verification Cleared 7/16/2020 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 7/16/2020 DAVID URITA
DAS Clearance Cleared 9/15/2020 EDDIE GARIN
Fire Marshall Fire Life Safety Cleared 10/2/2020 PEJMAN NOORI
Motion picture studio Cleared 10/2/2020 PEJMAN NOORI

Contact Information

Contractor Intercon Contractors Inc; Lic. No.: 578327-B 1705 MEADOWS AVE      MANHATTAN BEACH, CA 90266

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 11/13/2020 Approved EDWIN GREGORYONA
Drywall Nailing 11/19/2020 Approved EDWIN GREGORYONA
Drywall Nailing 11/23/2020 Approved EDWIN GREGORYONA
Footing/Foundation/Slab 12/21/2020 Corrections Issued EDWIN GREGORYONA
Footing/Foundation/Slab 12/22/2020 Corrections Issued EDWIN GREGORYONA
Deputy Reinf. Masonry 12/29/2020 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 12/29/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Masonry 12/30/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 1/5/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/7/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 1/11/2021 Partial Inspection EDWIN GREGORYONA
Deputy Reinf. Masonry 1/12/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/13/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Masonry 1/14/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 2/9/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Masonry 2/17/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/5/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Masonry 3/19/2021 Partial Approval EDWIN GREGORYONA
Final 6/10/2021 Not Ready for Inspection RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Approved RUSSELL BONVOULOIR
Smoke Detectors 6/10/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Smoke Detectors 6/22/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Final 8/24/2021 Permit Finaled RUSSELL BONVOULOIR
Smoke Detectors 8/24/2021 Approved RUSSELL BONVOULOIR