10140 N MOUNTAIR AVE 91042

Certificate Information: 10140 N MOUNTAIR AVE 91042

Application / Permit
20016-10000-10987
Plan Check / Job No.
B20LA08184
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
VOLUNTARY SOFT-STORY RETROFIT FOR AN EXISTING THREE STORY APARTMENT BUILDING WITH THREE NEW ORDINARY STEEL MOMENT FRAMES. (see comments)
Permit Issued
Issued on 7/23/2021
Issuing Office
Current Status
Permit Finaled on 3/11/2022

Permit Application Status History

Submitted 5/6/2020 APPLICANT
Assigned to Plan Check Engineer 6/3/2020 HANS SANTIAGO
Corrections Issued 6/10/2020 HANS SANTIAGO
Quality Review Completed 6/12/2020 SAI KHUM
Building Plans Picked Up 6/17/2020 APPLICANT
Applicant returned to address corrections 7/21/2020 HANS SANTIAGO
Plan Check Approved 9/8/2020 ANDREW SANTIAGO
Plan Check Approved 9/10/2020 ANDREW SANTIAGO
Issued 7/23/2021 APPLICANT
Permit Finaled 3/11/2022 ANDREW DORSO

Permit Application Clearance Information

Specific Plan Cleared 7/8/2020 DANIEL CORONADO
Grading Pre-Inspection Cleared 7/14/2020 KIRK LINKLATER
Tenant Habitability Plan Cleared 7/20/2021 MICHAEL SOTO

Contact Information

Contractor Decoma Structural Industries Inc; Lic. No.: 751888-B 921-A VAN NESS AVE      TORRANCE, CA 90501
Engineer Givechi,, Mehrzad; Lic. No.: C45725 344 VIA COLUSA      REDONDO BEACH, CA 90277

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2021 Corrections Issued ANDREW DORSO
Deputy Steel/Welding 11/22/2021 Conditional Approval ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 12/6/2021 Partial Inspection ANDREW DORSO
Wood Frame 12/6/2021 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 12/20/2021 Conditional Approval ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 12/21/2021 Partial Inspection ANDREW DORSO
Wood Frame 12/21/2021 Partial Inspection ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 12/30/2021 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 12/30/2021 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 1/4/2022 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 1/18/2022 Conditional Approval ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 1/25/2022 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 1/27/2022 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 2/1/2022 Conditional Approval ANDREW DORSO
Floor/Roof Diaphrgm/Shear Wall 2/2/2022 Approved ANDREW DORSO
Structural Steel Frame 2/2/2022 Approved ANDREW DORSO
Interior/Exterior Lathing 2/25/2022 Approved ANDREW DORSO
Final 3/11/2022 Permit Finaled ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Approved ANDREW DORSO
Smoke Detectors 3/11/2022 Approved ANDREW DORSO