4765 W DON MIGUEL DR 90008
Certificate Information: 4765 W DON MIGUEL DR 90008
- Application / Permit
- 20016-10000-10975
- Plan Check / Job No.
- B20LA08174
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (3) STEEL SPECIAL CANTILEVER COLUMN.
- Permit Issued
- Issued on 11/9/2020
- Issuing Office
- Current Status
- CofC Issued on 4/29/2024
Permit Application Status History
| Submitted | 5/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2020 | DANIEL SANJUAN |
| Corrections Issued | 6/17/2020 | DANIEL SANJUAN |
| Quality Review Completed | 6/18/2020 | SAI KHUM |
| Plan Check Approved | 10/15/2020 | DANIEL SANJUAN |
| Issued | 11/9/2020 | APPLICANT |
| OK for CofC | 3/6/2024 | DARRYL ARNOLD |
| CofC Issued | 4/29/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 11/4/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Park,, Kenan; Lic. No.: C86314 | 904 S HARVARD BLVD APT 208 LOS ANGELES, CA 90006 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/25/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/7/2021 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 9/8/2021 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 9/30/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 9/30/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/5/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 6/3/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 6/3/2022 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 6/3/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 6/3/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 8/17/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 8/17/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 8/17/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 1/22/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 1/22/2024 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 1/22/2024 | Corrections Issued | DARRYL ARNOLD |
| Final | 3/6/2024 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 3/6/2024 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 3/6/2024 | Approved | DARRYL ARNOLD |