16742 W BERMUDA ST 91344

Certificate Information: 16742 W BERMUDA ST 91344

Application / Permit
20016-10000-10962
Plan Check / Job No.
B20LA08167
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Ref# 4571. Convert existing accessory building to detached ADU per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 7/7/2020
Issuing Office
Current Status
CofO Issued on 12/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2020 APPLICANT
Assigned to Plan Check Engineer 5/14/2020 HELEN NGUYEN
Corrections Issued 5/22/2020 HELEN NGUYEN
Quality Review Completed 5/28/2020 PRANITA SHAH
Applicant returned to address corrections 6/19/2020 HELEN NGUYEN
Plan Check Approved 7/2/2020 HELEN NGUYEN
Issued 7/7/2020 APPLICANT
CofO in Progress 11/3/2020 MARK JOHNSON
CofO Issued 12/12/2020 MICHAEL SMITH
Permit Finaled 12/12/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/9/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/9/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/18/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Landers,, Jesse Eugene; Lic. No.: C83060 2101 BENECIA AVE      LOS ANGELES, CA 90025

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deck 7/28/2020 Not Ready for Inspection MICHAEL TEMPLE
Underground Mechanical 7/28/2020 Partial Approval MICHAEL TEMPLE
Sewer 7/31/2020 Approved MARK JOHNSON
Footing/Foundation/Slab 8/4/2020 Approved MARK JOHNSON
ELECTRICAL-Rough 8/14/2020 Approved MARK JOHNSON
PLUMBING-Rough 8/14/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 8/18/2020 Partial Approval MICHAEL TEMPLE
Green Building Rough 8/18/2020 Not Ready for Inspection MICHAEL TEMPLE
HVAC-Rough 8/18/2020 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 8/31/2020 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 8/31/2020 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Approved JENNIFER RABUCHIN
Green Building Rough 8/31/2020 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 8/31/2020 Partial Approval JENNIFER RABUCHIN
Insulation 8/31/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 8/31/2020 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/8/2020 Partial Approval MARK JOHNSON
Drywall Nailing 9/8/2020 Partial Inspection MARK JOHNSON
Green Building Rough 9/8/2020 Approved MARK JOHNSON
HVAC-Rough 9/8/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 9/8/2020 Approved MARK JOHNSON
Shower Pan 9/8/2020 Not Ready for Inspection MARK JOHNSON
Interior/Exterior Lathing 9/14/2020 Approved DAVID SCANTLIN
Shower Pan 9/14/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/22/2020 Approved MARK JOHNSON
Drywall Nailing 10/22/2020 Approved MARK JOHNSON
Final 10/22/2020 Corrections Issued MARK JOHNSON
Green Building Final 10/22/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 10/22/2020 SGSOV Approved MARK JOHNSON
Smoke Detectors 10/22/2020 Approved MARK JOHNSON
Final 11/2/2020 OK to Issue CofO MARK JOHNSON