8428 S FORDHAM ROAD 90045

Certificate Information: 8428 S FORDHAM ROAD 90045

Application / Permit
20016-10000-10949
Plan Check / Job No.
B20LA08151
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT [18' x 20'] DETACHED GARAGE TO STUDIO ADU. NEW KITCHEN AND 3/4 BATHROOM. PROVIDE TWO OPEN PARKING SPACES.
Permit Issued
Issued on 6/24/2020
Issuing Office
Current Status
CofO Issued on 3/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 JESSE JIMENEZ
Corrections Issued 5/7/2020 JESSE JIMENEZ
Applicant returned to address corrections 6/1/2020 ADAM HEGAZI
Applicant returned to address corrections 6/16/2020 JESSE JIMENEZ
Plan Check Approved 6/18/2020 JESSE JIMENEZ
Issued 6/24/2020 APPLICANT
Building Plans Picked Up 6/25/2020 APPLICANT
CofO in Progress 3/3/2021 MARIAN PODPORA
Permit Finaled 3/17/2021 BRUCE TODD
CofO Issued 3/17/2021 BRUCE TODD
Permit Finaled 3/17/2021 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 5/22/2020 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 5/22/2020 HISASHI KOBAYAKAWA
Permit Cleared 5/22/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 5/22/2020 HISASHI KOBAYAKAWA
Specific Plan Cleared 6/9/2020 VALERIA CEJA

Contact Information

Contractor Owner-Builder       ,
Engineer Javadvesian,, Hrach; Lic. No.: C42319 411 N CENTRAL 605      GLENDALE, CA 91203

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/30/2020 Not Ready for Inspection JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Partial Approval MARIAN PODPORA
Footing/Foundation/Slab 7/16/2020 Approved MARIAN PODPORA
ELECTRICAL-Rough 8/10/2020 Corrections Issued RYAN BARNES
Gas Test 8/10/2020 Approved RYAN BARNES
HVAC-Rough 8/10/2020 Corrections Issued RYAN BARNES
PLUMBING-Rough 8/10/2020 Approved RYAN BARNES
Wood Frame 8/10/2020 Conditional Approval RYAN BARNES
HVAC-Rough 8/17/2020 Approved RYAN BARNES
Insulation 8/17/2020 Approved RYAN BARNES
Drywall Nailing 8/21/2020 Approved RYAN BARNES
Interior/Exterior Lathing 8/27/2020 Partial Approval MARIAN PODPORA
Shower Pan 9/8/2020 Approved MARIAN PODPORA
Interior/Exterior Lathing 9/9/2020 Partial Approval MARIAN PODPORA
BUILDING-Rough-Frame 12/23/2020 Approved JOHN MATTILLO
Final 12/23/2020 Corrections Issued JOHN MATTILLO
Green Building Final 12/23/2020 Corrections Issued JOHN MATTILLO
Green Building Rough 12/23/2020 Approved JOHN MATTILLO
SGSOV-Seismic Gas S/O Valve 12/23/2020 SGSOV Approved JOHN MATTILLO
Smoke Detectors 12/23/2020 Approved JOHN MATTILLO
Final 1/21/2021 Corrections Issued MARIAN PODPORA
Green Building Final 1/21/2021 Approved MARIAN PODPORA
Pre-Inspection 2/22/2021 Not Ready for Inspection MARIAN PODPORA
Final 3/2/2021 Conditional Approval MARIAN PODPORA
Gas Test 3/2/2021 Approved MARIAN PODPORA