3106 1/2 W BERKELEY AVE 90026
Certificate Information: 3106 1/2 W BERKELEY AVE 90026
- Application / Permit
- 20016-10000-10935
- Plan Check / Job No.
- B20LA08139
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (E) 3 CAR GARAGE TO BE CONVERTED TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 8/6/2020
- Issuing Office
- Current Status
- CofO Issued on 11/25/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 5/7/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/13/2020 | ZAW HAN |
| Plan Check Approved | 7/27/2020 | ZAW HAN |
| Issued | 8/6/2020 | APPLICANT |
| Building Plans Picked Up | 8/10/2020 | APPLICANT |
| CofO in Progress | 11/25/2020 | HAMIK HARTOUNIAN |
| Permit Finaled | 11/25/2020 | DEROLD HAUFF |
| CofO Issued | 11/25/2020 | DEROLD HAUFF |
| Permit Finaled | 11/25/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 6/18/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/13/2020 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 8/18/2020 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 9/8/2020 | Partial Approval | ENRIQUE MIRELES |
| Wood Frame | 9/8/2020 | Partial Approval | ENRIQUE MIRELES |
| Insulation | 9/11/2020 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 9/11/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 9/15/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/15/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 9/15/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/17/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 11/17/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2020 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/17/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 11/24/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Pre-Inspection | 11/24/2020 | Approved | HAMIK HARTOUNIAN |