3106 1/2 W BERKELEY AVE 90026

Certificate Information: 3106 1/2 W BERKELEY AVE 90026

Application / Permit
20016-10000-10935
Plan Check / Job No.
B20LA08139
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(E) 3 CAR GARAGE TO BE CONVERTED TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 8/6/2020
Issuing Office
Current Status
CofO Issued on 11/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 FARSHAD ALIMOHAMADI
Corrections Issued 5/7/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/13/2020 ZAW HAN
Plan Check Approved 7/27/2020 ZAW HAN
Issued 8/6/2020 APPLICANT
Building Plans Picked Up 8/10/2020 APPLICANT
CofO in Progress 11/25/2020 HAMIK HARTOUNIAN
Permit Finaled 11/25/2020 DEROLD HAUFF
CofO Issued 11/25/2020 DEROLD HAUFF
Permit Finaled 11/25/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/18/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 6/18/2020 EMIL KYUPELYAN
Sewer availability Cleared 6/18/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 8/13/2020 Partial Approval RUBEN SALAS
Excavation/Setback/Form/Re-Bar 8/18/2020 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 9/8/2020 Partial Approval ENRIQUE MIRELES
Wood Frame 9/8/2020 Partial Approval ENRIQUE MIRELES
Insulation 9/11/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 9/11/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 9/15/2020 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/15/2020 Partial Approval HAMIK HARTOUNIAN
Shower Pan 9/15/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/17/2020 Approved HAMIK HARTOUNIAN
Final 11/17/2020 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/17/2020 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 11/17/2020 Approved HAMIK HARTOUNIAN
Final 11/24/2020 OK to Issue CofO HAMIK HARTOUNIAN
Pre-Inspection 11/24/2020 Approved HAMIK HARTOUNIAN