9709 W VENICE BLVD 90034
Certificate Information: 9709 W VENICE BLVD 90034
- Application / Permit
- 20016-10000-10744
- Plan Check / Job No.
- B20LA08014
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: INSTALL SPECIAL STEEL CANTILEVER COLUMN.
- Permit Issued
- Issued on 12/16/2021
- Issuing Office
- Current Status
- CofC Issued on 7/18/2022
Permit Application Status History
| Submitted | 5/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2020 | DANIEL SANJUAN |
| Corrections Issued | 6/17/2020 | DANIEL SANJUAN |
| Quality Review Completed | 6/18/2020 | SAI KHUM |
| Disabled Access Plans Picked Up | 12/29/2020 | APPLICANT |
| Plan Check Approved | 11/8/2021 | DANIEL SANJUAN |
| Issued | 12/16/2021 | APPLICANT |
| OK for CofC | 7/13/2022 | GRANT WOODS |
| CofC Issued | 7/18/2022 | DAVID TSAU |
Permit Application Clearance Information
| DAS Clearance | Cleared | 7/8/2021 | DANIEL SANJUAN |
| Tenant Habitability Plan | Cleared | 11/30/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 19528 VENTURA BLVD #300 TARZANA, CA 91356 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/28/2021 | Approved | GRANT WOODS |
| Deputy Drilled-In Anchors | 2/4/2022 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 2/4/2022 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 2/11/2022 | Approved | JOHN DODGE |
| Structural Steel Frame | 2/11/2022 | Approved | JOHN DODGE |
| Wood Frame | 2/11/2022 | Partial Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 2/16/2022 | Conditional Approval | JOHN DODGE |
| Wood Frame | 2/23/2022 | Approved | BRUCE CAMPBELL |
| Pre-Inspection | 3/8/2022 | Partial Inspection | GRANT WOODS |
| Interior/Exterior Lathing | 3/23/2022 | Approved | GRANT WOODS |
| Final | 7/1/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Not Ready | PAUL DAVIDSON |
| Smoke Detectors | 7/1/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Final | 7/13/2022 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 7/13/2022 | Approved | GRANT WOODS |