1526 N AVENUE 50 90042

Certificate Information: 1526 N AVENUE 50 90042

Application / Permit
20016-10000-10652
Plan Check / Job No.
B20LA07943
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXISTING 1-STORY SFD 1,439 SF TO BE REMODELED. 2 BEDROOMS, 1 BATHROOM, KITCHEN REMODEL & NEW 1 MASTER BEDROOM WITH W.I.C. AND 1 BATHROOM.
Permit Issued
Issued on 1/29/2021
Issuing Office
Current Status
Permit Finaled on 5/22/2022

Permit Application Status History

Submitted 5/1/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 SAMUEL GONZALEZ
Corrections Issued 5/25/2020 SAMUEL GONZALEZ
Quality Review Completed 5/28/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 7/10/2020 APPLICANT
Plan Check Approved 8/3/2020 SAMUEL GONZALEZ
Building Plans Picked Up 8/7/2020 APPLICANT
Issued 1/29/2021 APPLICANT
Permit Finaled 5/19/2022 CRAIG VAUGHAN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/9/2020 PATRICK MISCHLICH
Green Code Cleared 7/9/2020 KHEDER ALRAZAA

Contact Information

Contractor Stonewall Structures Inc; Lic. No.: 1002156-B PO BOX 543      CLAREMONT, CA 91711
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 7333 RANCHITO AVE      VAN NUYS, CA 91405

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/4/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 2/11/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/22/2021 Approved CRAIG VAUGHAN
Wood Frame 4/19/2021 Corrections Issued CRAIG VAUGHAN
Interior/Exterior Lathing 5/17/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 5/17/2021 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 10/7/2021 Partial Approval CRAIG VAUGHAN
Wood Frame 10/28/2021 Approved CRAIG VAUGHAN
Insulation 1/12/2022 Approved CRAIG VAUGHAN
Drywall Nailing 2/11/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 2/11/2022 Approved CRAIG VAUGHAN
Final 5/11/2022 Corrections Issued CRAIG VAUGHAN
Green Building Final 5/11/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 5/11/2022 Corrections Issued CRAIG VAUGHAN
Final 5/17/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 5/17/2022 Approved CRAIG VAUGHAN
Final 5/19/2022 Permit Finaled CRAIG VAUGHAN