1526 N AVENUE 50 90042
Certificate Information: 1526 N AVENUE 50 90042
- Application / Permit
- 20016-10000-10652
- Plan Check / Job No.
- B20LA07943
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXISTING 1-STORY SFD 1,439 SF TO BE REMODELED. 2 BEDROOMS, 1 BATHROOM, KITCHEN REMODEL & NEW 1 MASTER BEDROOM WITH W.I.C. AND 1 BATHROOM.
- Permit Issued
- Issued on 1/29/2021
- Issuing Office
- Current Status
- Permit Finaled on 5/22/2022
Permit Application Status History
| Submitted | 5/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 5/25/2020 | SAMUEL GONZALEZ |
| Quality Review Completed | 5/28/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 7/10/2020 | APPLICANT |
| Plan Check Approved | 8/3/2020 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 8/7/2020 | APPLICANT |
| Issued | 1/29/2021 | APPLICANT |
| Permit Finaled | 5/19/2022 | CRAIG VAUGHAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/9/2020 | PATRICK MISCHLICH |
| Green Code | Cleared | 7/9/2020 | KHEDER ALRAZAA |
Contact Information
| Contractor | Stonewall Structures Inc; Lic. No.: 1002156-B | PO BOX 543 CLAREMONT, CA 91711 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/4/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 2/11/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/22/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 4/19/2021 | Corrections Issued | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 5/17/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 5/17/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 10/7/2021 | Partial Approval | CRAIG VAUGHAN |
| Wood Frame | 10/28/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 1/12/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 2/11/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/11/2022 | Approved | CRAIG VAUGHAN |
| Final | 5/11/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 5/11/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 5/11/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 5/17/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 5/17/2022 | Approved | CRAIG VAUGHAN |
| Final | 5/19/2022 | Permit Finaled | CRAIG VAUGHAN |